Strand Hunt Construction, Inc. appealed a contracting officer's decision denying its claim for costs related to excessive heat conditions during contract performance. The Board denied the appeal.

Material Facts

  • The United States Army Corps of Engineers entered into fixed-price Contract No. DACA85-03-C-0007 with SHCI for the design and construction of emission reduction baghouse facilities.
  • The face amount of the contract was $21,719,361.
  • The contract contained several standard FAR provisions.
  • The specifications described indoor temperatures at the CHPP as high as 140°F.
  • SHCI submitted a request for equitable adjustment (REA) for $2,447,453 due to excessive heat conditions.
  • The CO denied SHCI's claim, concluding that the high temperatures did not constitute a changed condition.

Parties

Appellant
Strand Hunt Construction, Inc.
Respondent Agency
U.S. Army Engineer District, Alaska
Contract Number
Contract No. DACA85-03-C-0007
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.