Zafer Construction Company
Zafer Construction Company appealed a decision regarding its claim for additional compensation under Contract No. W917PM-05-C-0005 for renovation work at a military hospital in Afghanistan, alleging unilateral mistake and differing site conditions. The Board denied the appeal.
Material Facts
- Zafer Construction Company entered into Contract No. W917PM-05-C-0005 with the U.S. Army Corps of Engineers for renovation work on a military hospital in Kabul, Afghanistan.
- Zafer sought an additional $4,104,891 for work it claimed was not included in its original proposal.
- The Board found that Zafer did not conduct a site visit prior to submitting its proposal.
- Zafer's proposal was based on the Baker sketches provided by the government, which did not include all necessary details.
- The government conducted site visits that Zafer did not attend, and the solicitation included a Site Investigations clause requiring contractors to inspect the site.
Parties
- Appellant
- Zafer Construction Company
- Respondent Agency
- U.S. Army Corps of Engineers
- Contract Number
- W917PM-05-C-0005
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Patriot Construction, LLCNo. 63087-ADR, 63205-ADRMay 15, 2025
- Red River Science & Technology, LLCNo. 63785April 22, 2025
- Teledyne Scientific & Imaging, LLCNo. 62716, 62717February 19, 2025
- Record Steel and Construction, Inc. dba RSCINo. 63639June 24, 2024
- Record Steel and Construction, Inc. dba RSCINo. 63563June 24, 2024
- AVMAC LLCNo. 63747-ADRMay 24, 2024
Same Year
- Columbia State Bank f/k/a Castle-Rose, Inc.No. 59531December 28, 2017
- Fluor Federal Solutions, LLCNo. 61431-983December 28, 2017
- Goodwill Services, Inc.No. 61439December 27, 2017
- Suffolk Construction Company, Inc.No. 60990December 27, 2017
- Parsons Government Services, Inc.No. 60218December 21, 2017
- Parsons Government Services, Inc.No. 60221December 21, 2017
Same Issue
- Bodell Construction CompanyNo. 63517-ADR, 63850-ADROctober 2, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- WSP USA Solutions Inc.No. 62674September 1, 2026
- Mvation Worldwide Inc.No. 64633August 18, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026