Huffman Construction, LLC

September 30, 2026Judge Hamady
Denied / Government PrevailedTermination for DefaultDelay / Disruption / SuspensionContract InterpretationQuantum / DamagesAuthority of Government AgentsStatutory ComplianceAccord & Satisfaction / Release / WaiverAI Citation Misuse

Huffman Construction, LLC challenged the default termination of its fixed-price construction contract and sought a time extension and monetary relief based on alleged delays involving government-furnished pumps and motors. The Board denied both appeals, holding that Huffman failed to prove excusable critical-path delay and that the contracting officer's termination decision was neither arbitrary nor capricious.

Material Facts

  • The Corps awarded Huffman Contract No. W912EQ-14-C-0028 for completion of the Grand Prairie Pumping Station, including installation of government-furnished pumps and motors.
  • The final contract completion date established by bilateral Modification No. P00018 was December 15, 2019.
  • Huffman did not complete the work by the contract completion date.
  • The contract required Huffman to install and test the government-furnished equipment and to perform pump and motor work under the guidance of factory-trained manufacturer representatives.
  • The contract required schedule updates using a critical-path network and stated that time extensions would not be granted unless delay impacted the critical path, consumed available float or contingency time, and extended work beyond the completion date.
  • The pump and motor work was not shown on Huffman's contemporaneous schedule updates as controlling the project's critical path.
  • Huffman did not provide measurement data showing that the sole plates were installed within the required tolerance when installed.
  • Huffman did not identify a specific defect in the government-furnished pumps or motors.
  • Huffman's progress on non-pump and motor work was slow, the project remained at 95% completion for an extended period, and Huffman's workforce declined before termination.
  • Huffman's delay expert inserted pump-delay and removal-and-reinstallation activities into schedules and treated the resulting period as excusable delay.
  • The contracting officer issued a pre-termination letter and final decision addressing Huffman's performance failures and asserted excuses.
  • The contracting officer terminated the contract for default on March 31, 2020.

Parties

Appellant
Huffman Construction, LLC
Respondent Agency
U.S. Army Corps of Engineers
Contracting Agency
U.S. Army Corps of Engineers
Contract Number
W912EQ-14-C-0028
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.