U.S. Aeroteam, Inc.

August 6, 2026Judge O'Connell
Partially SustainedCost Allowability / Allocability (FAR 31)Contract Changes / Constructive ChangesDelay / Disruption / SuspensionDefective SpecificationsInspection / Acceptance / Warranty / Latent DefectsQuantum / DamagesAuthority of Government AgentsCDA JurisdictionContract InterpretationAccord & Satisfaction / Release / WaiverDCMA Involved

U.S. Aeroteam, Inc. appealed claims arising from two Air Force firm-fixed-price contracts for ground support trailers, principally seeking equitable adjustments for alleged technical-data-package defects, delay, disruption, inspection, and related costs. The Board dismissed portions for lack of jurisdiction or claim preclusion, sustained the appeals as to shoring, consultant costs, and in-house REA-preparation costs, and denied the remaining claims.

Material Facts

  • The Air Force awarded USAT two firm-fixed-price contracts for ground support trailers for C-17 Globemaster III aircraft engines.
  • The contracts placed maximum risk and full responsibility for costs and resulting profit or loss on USAT.
  • The contracts included a technical data package containing approximately 800 drawings and numerous identified parts.
  • USAT obtained running gear from PDI, later chose to manufacture the running gear itself after PDI increased its price, and experienced quality and production problems.
  • USAT previously litigated running-gear claims in the Court of Federal Claims, which ruled for the government, and the Federal Circuit affirmed.
  • USAT's later Factor 11 claims alleged interruption to production and consistent non-responsiveness arising from engineering orders and alleged technical-data-package defects.
  • USAT's Factor 11 evidence included spreadsheets and general witness testimony but did not identify the length of individual delays or reliably establish the claimed overall delay.
  • The government was responsible for obtaining carriers to transport the trailers, and carriers frequently failed to arrive or arrived with incorrect equipment.
  • USAT staged trailers for pickup and had to remove and restage them when carriers lacked suitable trucks or equipment.
  • The contracting officer had placed deliveries on hold because of recurring brake problems, causing storage and work-around costs for trailers occupying USAT's facility.
  • USAT incurred consultant and in-house labor costs in preparing and negotiating the REAs.
  • USAT omitted the required first two zeros from identification-tag serial numbers and did not produce evidence that tag replacement was economically wasteful.

Parties

Appellant
U.S. Aeroteam, Inc.
Respondent Agency
Air Force
Contracting Agency
Air Force
Contract Number
FA8526-09-C-0007; FA8526-12-C-0039
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.