ESCgov, Inc. appealed from the deemed denial of its contract termination for convenience claim under Contract No. HC1028-12-C-0047, resulting in a partial award.

Material Facts

  • The 2008 contract was awarded to ESCgov on 21 April 2008 for a base period of one year with two option periods.
  • Modification No. P00005 changed the start date of the base period to 1 February 2009.
  • The 2012 contract was awarded to ESCgov on 24 July 2012 and included a base year amount of $2,276,906.
  • A protest was filed on 1 August 2012, leading to a stop work order issued on 10 August 2012.
  • The 2012 contract was terminated for convenience on 29 August 2012.
  • ESCgov submitted a termination settlement proposal seeking $3,384,500.76.
  • The contracting officer determined that only $180,937.50 was allowable, leading to the appeal.

Parties

Appellant
ESCgov, Inc.
Respondent Agency
Defense Information Systems Agency
Contract Number
HC1028-12-C-0047
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.