IAP Worldwide Services, Inc.

May 17, 2017Judge Melnick
Sustained / Appellant PrevailedSuperior KnowledgeContract Interpretation

IAP Worldwide Services, Inc. appealed against the U.S. Army Corps of Engineers regarding costs incurred due to a border closure in Pakistan affecting contract performance. The Board found in favor of IAP, recognizing an excusable delay and constructive acceleration.

Material Facts

  • IAP contracted with the U.S. Army Corps of Engineers to provide power plants at forward military bases in Afghanistan.
  • Pakistan closed its border in response to a military attack, which remained closed for seven months.
  • IAP sought recovery for costs incurred due to the border closure.
  • The government denied IAP's requests for extensions of delivery order performance periods after the border closed.
  • The government later recognized the border closure as an excusable delay but did not grant sufficient extensions.

Parties

Appellant
IAP Worldwide Services, Inc.
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
W912BU-10-D-0018
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.