63770

Inland Service Corporation, LLC

May 21, 2026Judge Laufgraben
Partially SustainedContract Changes / Constructive ChangesSuperior Knowledge

Inland Service Corporation, LLC appealed a decision regarding a requirements contract with the Army for solid-waste management services, contesting a 365-day completion period imposed by a task order. The Board denied the Army's summary judgment motion on the completion period but granted it on a superior knowledge claim.

Material Facts

  • Inland holds a requirements contract with the United States Army for solid-waste management services at Fort Hood, Texas.
  • The Army issued a task order directing Inland to construct a new landfill cell within 365 days.
  • Inland argued that the base contract did not specify a deadline for completion.
  • The Army's task order set a 336-day completion period, which was later extended to 365 days.
  • Inland completed the work within the completion period and submitted its final invoice.

Parties

Appellant
Inland Service Corporation, LLC
Respondent Agency
Department of the Army
Contract Number
Contract No. W91151-21-D-0006
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.