6352864067

ACC Construction Co., Inc.

July 16, 2026Judge Melnick
Partially SustainedDelay / Disruption / SuspensionLiquidated DamagesContract Changes / Constructive ChangesEquitable Adjustment (REA)Accord & Satisfaction / Release / WaiverCDA JurisdictionContract InterpretationPayment / Progress Payments / Financing

ACC Construction Co., Inc. appealed disputes arising from alleged COVID-19-related delays, liquidated damages, and the government's handling of those delays. The Board denied the government's partial motion to dismiss and motion for summary judgment, holding that the payment estimates did not constitute final decisions, the good-faith claim was presented to the contracting officer, and the government did not establish final payment, release, or accord and satisfaction as a bar.

Material Facts

  • The U.S. Army Engineer District, Louisville awarded ACC a construction contract for facilities at Fort A.P. Hill, Virginia.
  • The contract included FAR 52.233-1, FAR 52.243-4, FAR 52.249-10, FAR 52.211-12, FAR 52.232-5, and FAR 52.232-27.
  • The contract required liquidated damages of $1,670 for each calendar day of delay until the work was completed or accepted.
  • ACC reported COVID-19 impacts to the project, and the government issued modifications addressing portions of the COVID-related delays.
  • The October 8, 2020 bilateral modification extended the completion date by 20 days and released the government from liability attributable to the covered facts or circumstances.
  • ACC did not agree to unilateral Modification No. A00013, which extended the period of performance by two days for a stated COVID-19 delay period.
  • Payment estimates deducted incremental liquidated damages from multiple invoices, but the estimates were issued on the same standard form as routine payment estimates.
  • Mr. Cory Pugh signed several payment estimates but was the COR and was explicitly barred from obligating government payment or taking action that may affect contract funds.
  • ACO Michael Roach was delegated authority to perform administrative functions under FAR 42.302 and was authorized under 41 U.S.C. § 7103(a) to issue contracting officer decisions assessing liquidated damages.
  • ACC declined to execute the requested final-payment documentation and release because of unresolved DEQ, COVID-delay, modification, and liquidated-damages issues.
  • The government paid ACC the remaining $100 one week after declaring the work completed and accepted, without ACC requesting that payment or executing a release.
  • ACC's certified claim alleged COVID impacts, government refusal to timely address resulting delays, changes or constructive changes, breach concerning substantial completion, and breach of the implied duty of good faith and fair dealing.

Parties

Appellant
ACC Construction Co., Inc.
Respondent Agency
U.S. Army Corps of Engineers
Contracting Agency
U.S. Army Engineer District, Louisville
Contract Number
W912QR-17-C-0021
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.