59630

Supply & Service Team GmbH

March 1, 2017Judge Prouty
Sustained / Appellant PrevailedAccord & Satisfaction / Release / Waiver

Supply & Service Team GmbH appealed a decision regarding contract modifications and overbilling claims against the Army. The Board granted summary judgment in favor of the appellant, concluding that the Army could not challenge the payments made under the contract.

Material Facts

  • The contract required role-playing actors for military training, initially only German or English-speaking.
  • In late 2006, the Army modified the contract to include Arabic and other Middle-Eastern language speakers.
  • SST encountered difficulties obtaining COBs who spoke the newly-required languages due to security clearance issues.
  • The Army agreed to compensate SST for the costs incurred while potential COBs awaited security checks.
  • SST submitted a request for equitable adjustment for increased costs due to delays and submitted an invoice for €88,763.
  • The Army executed Modification No. 04 to Task Order 02, which finalized all actions under the contract.

Parties

Appellant
Supply & Service Team GmbH
Respondent Agency
Army
Contract Number
W912PB-06-D-0011
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.