No. 2014-1507

DayDanyon Corp. v. Department of Defense

Jan 9, 2015opinionAppeal from the ASBCA
AffirmedContract disputeNonprecedentialContractor appealed

Disposition

AFFIRMED

Affirmed. Read from the standalone disposition line the opinion closes on. The court left the decision below standing. That is a win for whoever prevailed below, which is the appellee.

Key Facts

Appellant
Daydanyon Corporation
Appellee
Department of Defense
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2014-1507
Decided
Jan 9, 2015

From the opinion's own decided line.

Matter
Contract dispute
Panel
DYK, REYNA, WALLACH
Opinion by
DYK

Appealed From

The Armed Services Board of Contract Appeals, the Contract Disputes Act board for the defense agencies and NASA.

Appeal from the Armed Services Board of Contract Appeals in Nos. 57611, 57681, 57717, Administrative Judge David W. James Jr

Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion9 pages, 12,914 characters, read from the court's own documentDecided Jan 9, 2015 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelDYK, REYNA, WALLACHOpinion byDYKNonprecedentialAffirmed
Appealed fromArmed Services Board of Contract Appeals57611, 57681, 57717Judge David W. James JrThe opinion states: Appeal from the Armed Services Board of Contract Appeals in Nos. 57611, 57681, 57717, Administrative Judge David W. James Jr
The opinion closes: AFFIRMED(the standalone disposition line)

Authorities cited

6 authorities read from this opinion's own text, grouped by the body of law each comes from. 5 open at a publisher or in this app; the rest are shown without a link because no published page for them was confirmed.

Tucker Act and the Judicial Code2
28 U.S.C. § 129128 U.S.C. § 1295

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

5 cases this opinion cites, in the order it first names them. 4 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

DAYDANYON CORPORATION,

Appellant,

v.

DEPARTMENT OF DEFENSE,

Appellee.

2014-1507

Appeal from the Armed Services Board of Contract

Appeals in Nos. 57611, 57681, 57717, Administrative

Judge David W. James Jr.

Decided: January 9, 2015

J OSEPH A. CAMARDO, J R., Camardo Law Firm, PC, of

Auburn, New York, for appellant.

A. BONDURANT ELEY , Trial Attorney, Commercial Lit-

igation Branch, Civil Division, United States Department

of Justice, of Washington, DC, for appellee. With her on

the brief were J OYCE F. BRANDA, Acting Assistant Attor-

ney General, ROBERT E. K IRSCHMAN, J R., Director, and

MARTIN F. H OCKEY , J R., Assistant Director.

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

Before DYK, REYNA, and WALLACH, Circuit Judges.

DYK, Circuit Judge.

DayDanyon Corporation (“DayDanyon”) appeals a decision of the Armed Services Board of Contract Appeals (the “Board”) granting summary judgment to the government on DayDanyon’s claim that the ordering deadline of the contract at issue was December 24, 2010, and that the government breached the contract by failing to order the guaranteed minimum quantity of Collapsible Joint Modular Intermodal Containers (“JMICs” or the “containers”) by that date. Because the Board correctly interpreted the contract ordering period as ending on April 23, 2011, we affirm.

BACKGROUND

On April 23, 2009, the Defense Supply Center Philadelphia (“DSCP”), now known as Defense Logistics Agency Troop Support (“DLATS”), awarded Contract No. SPMSED-09-D-0001 (the “contract”) to DayDanyon for JMICs for use by the Naval Sea Systems Command. The contract provides, in relevant part: This is a[n] Indefinite Quantity Contract. Orders may be issued on this contract for a period of TWO YEARS.

. . .

After First Article Test approval, the required delivery for production quantities under this contract is 120 days after the date of the resulting delivery orders.

The Guaranteed Minimum is a total of 500 containers, whether placed for a single CLIN, or combination of CLINS that collectively total 500 containers. The guaranteed minimum is 500 containers per year. Since this is a two year base contract the minimum quantity is multiplied by 2.

J.A. 196. The contract also incorporated several Federal Acquisition Regulation (“FAR”) provisions, including FAR 52.216-22 INDEFINITE QUANTITY (OCT 1995), which provides, in relevant part: (d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after Two Years[.]

J.A. 211; see also 48 C.F.R. § 52.216-22.1 FROM: DATE OF CONTRACT AWARD THROUGH: TWO (2) YEARS

1The contract also incorporated FAR 52.216-18, ORDERING (OCT 1995), which provides, in relevant part: (a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued—

On April 29, 2010, DSCP approved DayDanyon’s First Article Test sample, and authorized DayDanyon to begin production of the JMICs. On May 3, 2010, DSCP issued two delivery orders for a total of 500 units under the contract, each with a delivery date of August 31, 2010, 120 days following receipt of the order. As of November 23, 2010, the contracting officer had extended the delivery date of the orders to two dates in March 2011. DayDanyon did not deliver any JMICs to DSCP by the March 2011 delivery dates.

On April 6, 2011, DayDanyon sent the contracting officer a certified claim for $720,700.00, alleging that DSCP breached the contract by failing to order the guaranteed minimum of 1,000 JMICs by December 24, 2010. According to DayDanyon’s claim, although the contract had “a J.A. 210; see also 48 C.F.R. § 52.216-18. And FAR 52.216-9007, CONTRACT AND DELIVERY ORDER LIMITATIONS (JUL 2006), which provides, in relevant part:

(a) Delivery orders will specify delivery no less than 120 days from the date of the order.

. . .

(c) Guaranteed Minimum

(1) The Government guarantees that it will order under this contract . . . the following minimum, as applicable:

. . .

(ii) Base period of two or more years.

500 EA TOTAL (Quantity) multiplied by two[.]

J.A. 211; see also 48 C.F.R. § 52.216-9007.

two year base period running through April 23, 2011,” DSCP was required to order the 1,000 JMICs by December 24, 2010, 120 days prior to the conclusion of the base period, because the contract provided that “delivery orders will specify delivery no less than 120 days from the date of the order,” and because DayDanyon “shall not be required to make any deliveries under this contract after [t]wo [y]ears.” J.A. 522 (quoting J.A. 211). The contracting officer responded that DayDanyon’s claim was “premature” because “[t]he two year base period for [the contract] expires on April 23rd, 2011.” J.A. 526. On April 20, 2011, the contracting officer terminated the contract for default, leading to a default termination claim submitted by DayDanyon on July 11, 2011. On May 18, 2011, DayDanyon filed another claim, which was materially identical to the April 6, 2011, claim. On July 15, 2011, the contracting officer denied the May 18, 2011, claim, explaining that because the contract was terminated on April 20, 2011, prior to the April 23, 2011, expiration of the base period, the government was not required to order the remainder of the guaranteed minimum quantity of JMICs.

DayDanyon appealed to the Board, which consolidated DayDanyon’s appeals of three separate claims: (1) the default termination claim, No. 57681; (2) the April 6, 2011 claim, No. 57611; and (3) the May 18, 2011, claim, No. 57717. The Board dismissed the May 18, 2011, claim as duplicative of the April 6, 2011, claim. On the default termination claim, the Board denied the government’s motion for summary judgment. On DayDanyon’s breach claim, relating to the government’s failure to order the requisite number of JMICs, the Board granted the government’s motion for summary judgment because it rejected DayDanyon’s interpretation of the contract to require the government to order 1,000 JMICs by December 24, 2010, as opposed to April 23, 2011.

The government did not appeal the denial of summary judgment in DayDanyon’s default termination claim, and proceedings with respect to that claim remain ongoing before the Board. We need not and do not decide

DayDanyon appeals. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10). We review the Board’s legal determinations, including interpretations of contracts, de whether the government properly terminated the contract for default.

Our jurisdictional statute provides jurisdiction to this court over “an appeal from a final order or final decision” of the Board. 28 U.S.C. § 1295(a)(10). In this case, despite the ongoing Board proceedings over the default termination claim, we have jurisdiction to review the separate breach of contract claims. See Dewey Elecs. Corp. v. United States, 803 F.2d 650, 653–54 (Fed. Cir. 1986) (“In this case, multiple claims are involved and, while there might be a question as to whether the remanded claims meet the finality requirement, the claims involved in this appeal were decided with finality.” (citations omitted)); see also Brownlee v. Dyncorp, 349 F.3d 1343, 1347 (Fed. Cir. 2003) (“Although [28 U.S.C. § 1295(a)(10)] requires that the Board’s decision be ‘final,’ we have held that the concept of finality in this context is more flexible than, for example, the ‘rigid district court concept of finality’ required by 28 U.S.C. § 1291.”) (quoting Dewey, 803 F.2d at 655)); Elkins v. Gober, 229 F.3d 1369, 1373–74 (Fed. Cir. 2000) (“This court has held, when reviewing decisions of agency boards of contract appeals, that a litigant’s individual claims for relief may, in certain circumstances, be separable for purposes of appellate review.” (citations omitted)).

novo. Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335–36 (Fed. Cir. 2013) (citations omitted).

DISCUSSION

The parties do not dispute that the contract required the government to order 1,000 JMICs prior to the termination of the contract, and that the government only ordered 500 JMICs before December 24, 2010. Instead, the dispute is over the date by which the government was required to order the additional 500 JMICs. DayDanyon contends that the applicable deadline was December 24, 2010, 120 days prior to the end of the two-year ordering period provided in the contract. The government responds that the deadline was April 23, 2011, the end of the two-year ordering period.

DayDanyon’s contention is refuted by the plain language of the contract, which clearly provides for a two-year ordering period. See Bell/Heery v. United States, 739 F.3d 1324, 1331 (Fed. Cir. 2014) (“When interpreting a contract, if the provisions are clear and unambiguous, they must be given their plain and ordinary meaning.” (citations and quotation marks omitted)). The contract unambiguously provides that “[o]rders may be issued on this contract for a period of TWO YEARS.” J.A. 196. This language is repeated in the contract’s incorporation of FAR 52.216-18, which provides that “orders may be issued” from the “DATE OF CONTRACT AWARD [April 23, 2009]” through “TWO (2) YEARS.” J.A. 210; see also J.A. 211 (checking the box adjacent to “Base period of two or more years.”).

The contract is ambiguous, however, as to orders placed by the government within 120 days of the conclusion of the two-year ordering period. This is because FAR 52.216-22(d) is subject to two plausible interpretations. On the one hand, the first sentence of FAR 52.216-22(d) provides that orders placed during the effective period of

the contract but not completed during the effective period “shall be completed by the Contractor within the time specified in the order,” i.e., within 120 days. J.A. 211. Under this reading, the proviso that the “Contractor shall not be required to make any deliveries under this contract after Two Years,” id., simply emphasizes that the contractor need not deliver orders that are placed by the government after April 23, 2011, the end of the two-year ordering period. On the other hand, as the government argues, the proviso could also be read to suggest that although the government may place orders at any time during the two-year ordering period, DayDanyon “shall not be required,” id., to make any deliveries placed within 120 days of April 23, 2011. We need not resolve this ambiguity as to whether the contractor is obligated to deliver orders placed within 120 days of the end of the two-year period, because regardless of which of the above interpretations is correct, the contract cannot mean what DayDanyon says it means—that the contract prohibits orders placed after December 24, 2010, 120 days prior to the conclusion of the two-year period.

As the Board found, DayDanyon’s interpretation, which reduces the effective ordering period of the contract from two years to twenty months, would render the contract’s incorporation of FAR 52.216-22(d) meaningless. See Bell/Heery, 739 F.3d at 1331 (“A contract must also be construed as a whole and in a manner that gives meaning to all of its provisions and makes sense.” (citations and quotation marks omitted)).

Thus, under the plain language of the contract, the government had until April 23, 2011, two years from the date of the contract award, to order the guaranteed minimum number of JMICs from DayDanyon whether or not DayDanyon was obligated to deliver beyond the two-year period. And as the Board found, because the government was not required to order the guaranteed minimum

amount of containers by December 24, 2010, the contractor’s claim was properly rejected.

AFFIRMED

This is a verbatim capture of the text layer of the court's own document in DayDanyon Corp. v. Department of Defense. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the ASBCA

Also Affirmed

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.