No. 2019-1608

United States Army Corps of Engineers v. John C. Grimberg Co.

Jun 9, 2020opinionAppeal from the ASBCA
ReversedContract disputeNonprecedentialContractor appealed

Disposition

REVERSED

Reversed. Read from the standalone disposition line the opinion closes on. The court held the decision below wrong and reversed it. The appellant prevailed.

Key Facts

Appellant
United States Army Corps of Engineers
Appellee
John C. Grimberg Co., Inc.
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2019-1608
Decided
Jun 9, 2020

From the opinion's own decided line.

Matter
Contract dispute
Panel
O’MALLEY, WALLACH, TARANTO
Opinion by
O’MALLEY

Appealed From

The Armed Services Board of Contract Appeals, the Contract Disputes Act board for the defense agencies and NASA.

Appeal from the Armed Services Board of Contract Ap peals in Nos. 58791, 59167, 59168, 59169, 59170, 59171, 59717, Administrative Judge J. Reid Prouty, Administra tive Judge Richard Shackleford, Administrative Judge Robert T. Peacock

Counsel

For the appellant
ALBERT S. IAROSSI
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellant
JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
HERMAN MARTIN BRAUDE
Braude Law Group, P.C
Rockville, MD
For the appellee
EDWARD JEROME PARROTT
Braude Law Group, P.C
Rockville, MD
For the appellee
Watt
Braude Law Group, P.C
Rockville, MD
For the appellee
Tieder
Braude Law Group, P.C
Rockville, MD
For the appellee
Hoffar & Fitzger- ald
Braude Law Group, P.C
Rockville, MD
For the appellee
McLean
Braude Law Group, P.C
Rockville, MD
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion8 pages, 14,365 characters, read from the court's own documentDecided Jun 9, 2020 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelO’MALLEY, WALLACH, TARANTOOpinion byO’MALLEYNonprecedentialReversed
Appealed fromArmed Services Board of Contract Ap peals58791, 59167, 59168, 59169, 59170, 59171, 59717Judge J. Reid ProutyThe opinion states: Appeal from the Armed Services Board of Contract Ap peals in Nos. 58791, 59167, 59168, 59169, 59170, 59171, 59717, Administrative Judge J. Reid Prouty, Administra tive Judge Richard Shackleford, Administrative Judge Robert T. Peacock
The opinion closes: REVERSED(the standalone disposition line)

Authorities cited

3 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Federal Acquisition Regulation1
Decisions of other forums1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

6 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 6 of them open, 1 in this app and 5 at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

NOTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

UNITED STATES ARMY CORPS OF ENGINEERS,

Appellant

v.

JOHN C. GRIMBERG CO., INC.,

Appellee

2019-1608

Appeal from the Armed Services Board of Contract Ap-

peals in Nos. 58791, 59167, 59168, 59169, 59170, 59171,

59717, Administrative Judge J. Reid Prouty, Administra-

tive Judge Richard Shackleford, Administrative Judge

Robert T. Peacock.

Decided: June 9, 2020

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
ALBERT S. IAROSSI
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

ALBERT S. IAROSSI, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellant. Also represented by JOSEPH H. HUNT, ALLISON KIDD -MILLER, ROBERT EDWARD KIRSCHMAN, JR.; SCOTT SEUFERT, United States Army Corps of Engineers, Baltimore, MD.

JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

Also represented by JOSEPH H.

For the appellee
HERMAN MARTIN BRAUDE
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

HERMAN MARTIN BRAUDE, Braude Law Group, P.C., Rockville, MD, argued for appellee. Also represented by EDWARD JEROME PARROTT, Watt, Tieder, Hoffar & Fitzger- ald, McLean, VA.

EDWARD JEROME PARROTT
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

Also represented by EDWARD JEROME PARROTT.

Watt
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

Also represented by Watt.

Tieder
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

Also represented by Tieder.

Hoffar & Fitzger- ald
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

Also represented by Hoffar & Fitzger- ald.

McLean
Braude Law Group, P.C
Rockville, MD
As the opinion writes it

Also represented by McLean.

ALBERT S. IAROSSI, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellant. Also represented by JOSEPH H. H UNT, ALLISON K IDD -M ILLER, R OBERT EDWARD K IRSCHMAN , JR.; SCOTT SEUFERT, United States Army Corps of Engineers, Baltimore, MD.

H ERMAN M ARTIN BRAUDE , Braude Law Group, P.C.,

Rockville, MD, argued for appellee. Also represented by EDWARD JEROME PARROTT, Watt, Tieder, Hoffar & Fitzgerald, McLean, VA.

Before O’MALLEY, WALLACH, and TARANTO, Circuit

Judges.

O’MALLEY, Circuit Judge.

The United States Army Corps of Engineers (“Corps”) appeals a decision of the Armed Services Board of Contract Appeals (“Board”) holding that John C. Grimberg Co., Inc. (“Grimberg”) is entitled to an equitable adjustment to the contract price for construction of the Navy Medical Biological Defense Research Laboratory (“Biolab”) in Fort Detrick, Maryland. John C. Grimberg Co., ASBCA Nos. 58791, 59167, 59168, 59169, 59170, 59171, 59717, 18-1 BCA ¶ 37,191. While we understand the Board’s desire to reach a conclusion it felt was not unjust in the circumstances, for the reasons discussed below, we must reverse.

I. BACKGROUND

The Corps issued a Request for Proposal (“RFP”) on February 23, 2009, seeking offers for the design and construction of the Biolab. The project entailed construction of a large laboratory building, an entry point building, parking facilities, an access road, stormwater management, and perimeter fencing. The RFP incorporated by reference the standard differing site condition (“DSC”) clause, as prescribed by 48 C.F.R. § 52.236-2, pursuant to which a contractor can ask for a cost adjustment if subsurface conditions at the construction site “differ materially from those indicated in the contract.”

The RFP also included, as an appendix, the “Geotechnical Report and Requirements” (“Geotechnical Report”). J.A. 4248–4423. The Geotechnical Report, although “preliminary” was meant to provide “bidders with sufficient

information to identify the general subsurface conditions of the site.” J.A. 4249. The Geotechnical Report stated that the Biolab should be supported by a deep foundation system of drilled piers (i.e., caissons or shafts) socketed into five feet of competent rock. J.A. 4256. The portion of the pier embedded in rock is called a “rock socket.”

To assist contractors in developing bids for the Biolab’s foundation, the Geotechnical Report disclosed 46 test borings to indicate the subsurface conditions at the project location. Eleven of the borings came from an investigation done during the construction of the National Interagency Bio-Defense Campus, of which the Biolab is a part. Just two of those borings, DH-11 and DH-12, were located within the planned footprint for the Biolab. Those two borings indicated high quality rock, with no intervening incompetent rock. The Geotechnical Report indicated, however, that contractors should not assume that the rock at the site would be free of voids given the information available from other borings. For example, certain borings taken between 300 and 500 feet from the Biolab footprint, in preparation for a different construction project, showed between 0 and 20 feet of incompetent rock.

Notably, the bedrock below the Biolab project, like the surrounding area, is limestone in a Karst formation. Karst geology is a condition of limestone rock that occurs when portions of the rock have been degraded over time by a Karst solutioning process. This process can create large cracks, fissures, and voids in the rock. As the Board explained, “Karst is a recognized geohazard, ‘[k]nown for its variability and its degree of inconsistency, both vertically and horizontally over extremely short distances.’” J.A. 2. In response to the Corps’ RFP, Grimberg submitted a proposal on March 31, 2009. Grimberg estimated that it would need to drill through 240 feet of rock (exactly 5 feet for each of 48 piers), at between $270 and $530 per foot, depending on the depth of the pier. This quote relied on

the testing results from DH-11 and DH-12, and assumed that excavation of incompetent rock would not be required as part of the construction.

On May 29, 2009, the Corps awarded the Biolab Project Contract to Grimberg. Grimberg proceeded on the contract and, once it began work on the foundation, quickly began to encounter incompetent rock. On March 10, 2010, Grimberg notified the Corps that it was encountering, in its view, a DSC. Grimberg ultimately drilled through 923 feet of rock—683 feet more than it had accounted for in its bid. J.A. 3435.

In May 2012, once the Biolab project was complete, Grimberg submitted a request for equitable adjustment of the contract price to the Corps, alleging a Type I DSC. J.A. 3449–3452. The request acknowledged that Grimberg relied on only DH-11 and DH-12 when structuring its bid. J.A. 3450. The letter further stated that Grimberg drilled through an average of 13.6 feet more rock per pier than expected to create the necessary rock sockets. J.A. 3451. The Corps denied Grimberg’s request in June 2012. In December, Grimberg submitted a certified claim. The Corps again denied the claim and Grimberg appealed to the Board.

The Board conducted an eight-day hearing and issued a lengthy opinion. Relevant to this appeal, the Board found that Grimberg encountered a Type I DSC. The Board explained that Grimberg met the standard for a Type I DSC because “[t]he quantities of rock encountered greatly exceeded the quantity reasonably foreseeable based on a fair reading of contractual indications.” J.A. 28. The Board found that Grimberg’s reliance on just two borings, DH-11 and DH-12, was unreasonable. J.A. 28–29; see also J.A. 31 (“Confronted with the plethora of cautionary contractual indications, ‘cherry picking’ a subset of 2 of 46 borings, regardless of their proximity to the Biolab foundation, was unjustifiable in the circumstances of this case.”). The

Board explained, however, that Grimberg’s reliance on two borings was more reasonable than the government’s proposal that Grimberg should have relied on borings located 300 to 500 feet from the Biolab footprint. J.A. 29. The Board explained:

a primary reason for our conclusion that [Grimberg] is entitled to relief despite its misreliance solely on DH-11 and DH-12, is the gross disparity between the quantities of incompetent rock actually encountered and the quantity that we consider was reasonably indicated in the contract’s Geotechnical Report. Even if it had expanded its pre-proposal analyses to include the seven most proximate borings to the Biolab site . . . or devoted the time and effort to analyze the 26 [other] borings as did the Corps at trial, the disparity was material and not reasonably foreseeable.

J.A. 29.

Having found that neither the Corps nor Grimberg provided a reasonable estimate of the amount of rock a reasonable contractor would have expected, the Board engaged in a “jury verdict” type analysis. J.A. 30. Based on the expert testimony and evidence presented at trial, it concluded that the contract reasonably indicated that 360 feet of rock drilling (an additional 2.5 feet per pier) would be required. Id. Because Grimberg actually encountered on average an additional 13.6 feet of incompetent rock, the Board found that Grimberg encountered more rock than was reasonably indicated in the contract. Id. Thus, the Board found for Grimberg on its DSC claim. The Board further found in favor of Grimberg on a claim for delays related to the DSC. J.A. 49.

The Corps filed a motion for reconsideration. In denying the motion, the Board explained that “[a]n ‘all or nothing’ resolution of this case would have been overly legalistic and unjust.” J.A. 70.

II. DISCUSSION

In an appeal from the Board, we review questions of law de novo. Rockies Exp. Pipeline LLC v. Salazar, 730 F.3d 1330, 1335 (Fed. Cir. 2013). The interpretation of contracts, statutes, and regulations is a question of law. Id. We review the Board’s factual findings to determine if the findings are arbitrary, capricious, or not supported by substantial evidence. Id.; 41 U.S.C. § 7107(b).

A Type I DSC exists when “subsurface or latent physical conditions at the site . . . differ materially from those indicated in [the] contract.” 48 C.F.R. § 52.236-2(a)(1). To establish an equitable adjustment to contract price based on a Type I DSC, a contractor must prove by a preponderance of the evidence:

[1] the conditions indicated in the contract differ materially from those actually encountered during performance; [2] the conditions actually encountered were reasonably unforeseeable based on all information available to the contractor at the time of bidding; [3] the contractor reasonably relied upon its interpretation of the contract and contract-related documents; and [4] the contractor was damaged as a result of the material variation between expected and encountered conditions.

Comtrol, Inc. v. United States, 294 F.3d 1357, 1362 (Fed. Cir. 2002); see also Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1581 (Fed. Cir. 1987). “While a contractor need not demonstrate that its interpretation of the contract is the only reasonable one, it does bear the burden of showing that its construction is at least a reasonable reading.” P.J. Maffei Bldg. Wrecking Corp. v. United States, 732 F.2d 913, 917 (Fed. Cir. 1984) (emphasis in original).

The Corps argues that the Board erred when it held that Grimberg is entitled to an equitable adjustment to

contract price despite having repeatedly stated that Grimberg’s interpretation of the contract was unreasonable. Grimberg does not respond to this contention. In fact, Grimberg fails to even address the governing legal standard in its briefing. Grimberg’s failure to contend with the required legal test is fatal to its claim.

For over thirty years, we have required that, to receive an equitable adjustment to the contract price, a contractor must prove that it reasonably relied on its interpretation of the contract. See Stuyvesant Dredging, 834 F.2d at 1581. Here, the Board found that Grimberg failed to do just that. See J.A. 28–29, 31. We are thus left with the inescapable conclusion that Grimberg has failed to prove its entitlement to an adjustment. The Board erred as a matter of law when it concluded otherwise.

The Board’s finding that the Corps’ interpretation was less reasonable than Grimberg’s does not change our conclusion. Appellee’s Br. 60–64. Despite the moniker “equitable adjustment” employed in this context, our case law does not permit us to balance the Corp’s reasonableness against that of the contractor. The focus of our inquiry must be on the reasonableness of the contractor. This focus serves the purpose of incentivizing contractors to carefully and reasonably interpret contract documents. See H.B. Mac, Inc. v. United States, 153 F.3d 1338, 1343 (Fed. Cir. 1998). In this case, the Corps chose to propose what it viewed as a “reasonable” interpretation of the contract to contrast with the “reasonable” interpretation proposed by Grimberg. That both the Corps and Grimberg failed in their endeavor to establish what would have been reasonable for this particular contract does not somehow shift the burden of providing a reasonable interpretation from Grimberg to the Corps. Regardless of the Corps’ understanding of the contract, our case law is clear that Grimberg must bear the risk of bidding on a contract without reasonably interpreting what that contract discloses.

The Board found more than once that Grimberg failed to prove that it reasonably relied on the test results from just two borings when formulating its Biolab bid. Because Grimberg was unreasonable, under long-established law, it is not entitled to an equitable adjustment of the contract price.

III. CONCLUSION

For the reasons discussed above, we reverse the Board’s holding that Grimberg is entitled to an equitable adjustment to contract price based on a Type I DSC.

REVERSED

While Grimberg dedicates a significant portion of its brief to summarizing the evidence it presented to the Board, see Appellee’s Br. 18–50, Grimberg does not directly challenge the Board’s finding that Grimberg’s interpretation of the contract was unreasonable, see id. at 58 (arguing that the Board’s interpretation of the contract was reasonable), 60 (arguing that the Board correctly rejected the Government’s interpretation of the contract as less reasonable than Grimberg’s). To the extent Grimberg challenges the Board’s factual finding that reliance on two borings was unreasonable, substantial evidence supports that finding.

This is a verbatim capture of the text layer of the court's own document in United States Army Corps of Engineers v. John C. Grimberg Co.. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the ASBCA

Also Reversed

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.