No. 2021-2272

U.S. Aeroteam, Inc. v. United States

Jul 5, 2022opinionAppeal from the Court of Federal Claims
AffirmedContract disputeNonprecedentialContractor appealed

Disposition

AFFIRMED

Affirmed. Read from the standalone disposition line the opinion closes on. The court left the decision below standing. That is a win for whoever prevailed below, which is the appellee.

Key Facts

Appellant
U.S. Aeroteam, Inc.
Appellee
United States
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2021-2272
Decided
Jul 5, 2022

From the opinion's own decided line.

Matter
Contract dispute
Panel
LOURIE, PROST, TARANTO
Opinion by
LOURIE

Appealed From

Court of Federal Claims1:18-cv-01096-MBH

The Article I trial court whose contract and bid protest judgments this court reviews under 28 U.S.C. 1295(a)(3).

Appeal from the United States Court of Federal Claims in No. 1:18-cv-01096-MBH, Senior Judge Marian Blank Horn

Counsel

For the appellant
MILTON C. JOHNS
Executive Law Partners, PLLC
Fairfax, VA
For the appellee
IGOR HELMAN
Commercial Litigation Branch, Civil Di- vision, United States Department of Justice
Washington, DC
For the appellee
BRIAN M
Commercial Litigation Branch, Civil Di- vision, United States Department of Justice
Washington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion11 pages, 19,079 characters, read from the court's own documentDecided Jul 5, 2022 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelLOURIE, PROST, TARANTOOpinion byLOURIENonprecedentialAffirmed
Appealed fromUnited States Court of Federal Claims1:18-cv-01096-MBHJudge Marian Blank HornThe opinion states: Appeal from the United States Court of Federal Claims in No. 1:18-cv-01096-MBH, Senior Judge Marian Blank Horn
The opinion closes: AFFIRMED(the standalone disposition line)

Authorities cited

2 authorities read from this opinion's own text, grouped by the body of law each comes from. 1 open at a publisher or in this app; the rest are shown without a link because no published page for them was confirmed.

Tucker Act and the Judicial Code2
28 U.S.C. § 129528 U.S.C. § 2111

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

11 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 8 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Other courts of appeals1
N. Ind. Pub. Serv. Co. v. Carbon County Coal Co.799 F.2d 265(7th Cir. 1986)

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

U.S. AEROTEAM, INC.,

Plaintiff-Appellant

v.

UNITED STATES,

Defendant-Appellee

2021-2272

Appeal from the United States Court of Federal Claims

in No. 1:18-cv-01096-MBH, Senior Judge Marian Blank

Horn.

Decided: July 5, 2022

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
MILTON C. JOHNS
Executive Law Partners, PLLC
Fairfax, VA
As the opinion writes it

MILTON C. JOHNS, Executive Law Partners, PLLC, Fairfax, VA, argued for plaintiff-appellant.

For the appellee
IGOR HELMAN
Commercial Litigation Branch, Civil Di- vision, United States Department of Justice
Washington, DC
As the opinion writes it

IGOR HELMAN, Commercial Litigation Branch, Civil Di- vision, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by BRIAN M. BOYNTON, LISA LEFANTE DONAHUE, PATRICIA M. MCCARTHY.

BRIAN M
Commercial Litigation Branch, Civil Di- vision, United States Department of Justice
Washington, DC
As the opinion writes it

Also represented by BRIAN M.

MILTON C. J OHNS , Executive Law Partners, PLLC, Fairfax, VA, argued for plaintiff-appellant.

I GOR HELMAN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by BRIAN M. B OYNTON, L ISA L EFANTE D ONAHUE, P ATRICIA M. MCCARTHY .

Before LOURIE, PROST, and TARANTO, Circuit Judges.

LOURIE, Circuit Judge.

U.S. Aeroteam, Inc. (“Aeroteam”) contracted with the United States Air Force to build ground support trailers. After Aeroteam incurred additional costs building the trailers, it requested compensation from the Air Force. The Air Force denied its request. Aeroteam filed a complaint at the United States Court of Federal Claims (“the Claims Court”). The Claims Court entered judgment in favor of the United States. U.S. Aeroteam, Inc. v. United States, No. 1:18-cv-01096-MBH (Fed. Cl. 2019), J.A. 3–9. We affirm the court’s judgment for the reasons explained below.

BACKGROUND

Aeroteam is a contractor that specializes in building components for the aerospace industry. In 2009, the Air Force awarded Aeroteam a contract to produce ground support trailers. J.A. 1709–10. The Air Force uses those trailers to transport aircraft engines. J.A. 1709.

In 2011, Aeroteam began having difficulties obtaining a key component of the trailers—the running-gear subassembly. J.A. 1712. The running gear is “essentially the drive train” for the trailer, “allow[ing] [it] to roll, brake, [and] steer.” J.A. 1710. To obtain the running gears, Aeroteam relied on PDI Ground Support Systems, an approved vendor under the contract. J.A. 1711–12. PDI initially charged Aeroteam $20,300 per unit. J.A. 1711. After facing financial difficulties, however, PDI raised its price. J.A. 7 (845:1–6). In response, Aeroteam decided to manufacture the running gears itself. According to Aeroteam, it could produce them “as well or better than PDI.”

Under the terms of the contract, Aeroteam could procure the running gears only from certain approved vendors, including PDI. J.A. 1710–11.

J.A. 1713–14; J.A. 1861 (342:3–12); J.A. 2125. Aeroteam was also concerned that PDI could not continue to supply it with the running gears in light of its financial situation. Appellant’s Br. 8. Subsequently, Aeroteam formally asked the Air Force if it could assume responsibility for manufacturing the running gears. J.A. 1714. Its request read, in relevant part, as follows:

US Aeroteam proposes to manufacture the entire running gear and brake system for TT90-F-507 Trailers Sernos 0020-0041 because PDI has refused to complete the contract as awarded.

J.A. 2125 (capitalization modified). The contracting officer approved Aeroteam’s request, stating that the manufacturing change was “acceptable.” J.A. 1715–16. On September 6, 2012, the Air Force awarded Aeroteam a second contract to produce additional trailers. J.A. 1716.

Shortly after Aeroteam began manufacturing the running gears for the trailers, it discovered that its costs were higher than it had expected. J.A. 7. As a result, Aeroteam sought to recoup those costs and filed a request for equitable adjustment in the amount of $1,385,912 for the first contract and $4,022,273 for the second contract. J.A. 29–30; Contract No. FA8526-09-C-0007 and Contract No. FA8526-12-C-0039. As relevant here, both of Aeroteam’s contracts were “firm-fixed-price,” meaning that they “place[d]” upon Aeroteam the “maximum risk and full responsibility for all costs and resulting profit or loss.” Federal Acquisition Regulation § 16.202-1; J.A. 1710, 1716. The contracting officer denied Aeroteam’s request for equitable adjustment. J.A. 1717. Aeroteam then filed a complaint at the Claims Court, alleging three grounds for recovery: (1) constructive change, i.e., the Air Force ordered Aeroteam, expressly or impliedly, to perform work beyond the contract requirements; (2) cardinal change, i.e., the Air Force effected an alteration in the work so drastic that it effectively required Aeroteam to perform duties materially different from those it originally bargained for; and (3) commercial impracticability, i.e., because of unforeseen events, Aeroteam could perform the contract only at an excessive and unreasonable cost or performance would be commercially senseless.

The government disputes Aeroteam’s assertion that PDI could no longer produce the running gears. We further address that argument below.

The Claims Court denied Aeroteam’s claims, issuing its decision from the bench without a subsequent written opinion. With respect to the constructive and cardinal change claims, the court held that Aeroteam had failed to prove that the Air Force ordered it to manufacture the running gears. Rather, according to the court, Aeroteam independently chose to do so. J.A. 7 (846:11–13); J.A. 8 (849:1–2). With respect to the commercial impracticability claim, the court found that Aeroteam could have continued to buy the running gears from PDI, albeit at a higher price. J.A. 5 (838:14–16). The court also pointed out that, because Aeroteam had entered into a fixed-price-contract, it assumed the risk that the price of the running gears would change. J.A. 6 (840:21–841:1); J.A. 7 (846:13–15).

After concluding that Aeroteam failed to prove its claims for recovery, the court entered judgment in favor of the government. J.A. 1. Aeroteam appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

This court reviews legal determinations of the Claims Court de novo and its findings of fact for clear error. Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1373 (Fed.

The Claims Court discussed cardinal change in conjunction with constructive change.

Cir. 2005) (citing Glendale Fed. Bank, FSB v. United States, 239 F.3d 1374, 1379 (Fed. Cir. 2001)). “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” United States v. U.S. Gypsum Co., 333 U.S. 364, 395 (1948).

Aeroteam argues that the Claims Court erred in denying its claims for (1) constructive change, (2) cardinal change, and (3) commercial impracticability. We address each argument in turn.

I

We turn first to Aeroteam’s argument regarding its constructive change claim. To demonstrate a constructive change, a contractor must show “(1) that it performed work beyond the contract requirements, and (2) that the additional work was ordered, expressly or impliedly, by the government.” Bell/Heery v. United States, 739 F.3d 1324, 1335 (Fed. Cir. 2014) (emphasis added) (citing Redland Co. v. United States, 97 Fed. Cl. 736, 755–56 (2011)). The parties’ dispute centers on the second element of constructive change.

Aeroteam argues that the Claims Court erred in denying its constructive change claim. According to Aeroteam, it did not choose to manufacture the running gears. Rather, the Air Force ordered it to make that change. The government responds that Aeroteam independently chose to manufacture the running gears, with no express or implied order from the Air Force.

We agree with the government that the Claims Court did not err in denying Aeroteam’s constructive change claim. As the Claims Court held, Aeroteam failed to prove that the Air Force ordered it to manufacture the running gears. J.A. 7 (846:11–15); J.A. 8 (849:1–8). On the contrary, that was “a choice that Aeroteam made.” J.A. 7

(846:11–13). Specifically, after learning of PDI’s financial difficulties, Aeroteam coordinated a plan to manufacture the running gears. Aeroteam did so because it was “confident that [it could] produce” the running gears “as well or better than PDI”—not because it was ordered to by the Air Force. J.A. 1713–14. Indeed, Aeroteam itself “propose[d]” to the Air Force that it “manufacture the entire running gear.” J.A. 2125 (emphasis added and capitalization modified). Moreover, Aeroteam acknowledged that it could not “do[] anything” with respect to manufacturing until it sought the Air Force’s approval. J.A. 1714–15. Accordingly, in view of the record before us, we see no clear error in the court’s determination.

Aeroteam makes several additional arguments, all unpersuasive. First, Aeroteam emphasizes that the Air Force approved its manufacturing request. According to Aeroteam, because of that approval, the Air Force effectively directed it to manufacture the running gears. We disagree. Mere approval, standing alone, is insufficient to prove constructive change. Rather, there must be an “order[],” either “express[] or implied[].” Bell/Heery, 739 F.3d at 1335 (citing Redland, 97 Fed. Cl. at 755–56). Accordingly, Aeroteam’s argument is unpersuasive.

Second, Aeroteam argues that the Claims Court “expand[ed] the requirements” necessary to prove a claim for constructive change. Appellant’s Br. 21. Specifically, Aeroteam points to portions of the court’s decision suggesting it was required to prove that the government authorized a “change in contract price.” See Appellant’s Br. 21–22; J.A. 6 (841:17–22) (“[T]he government . . . [did not take] that next step of authorizing or directing a change in the contract price.”) (emphasis added); J.A. 8 (849:9–11) (“The drawings, the expectation of whether the plaintiff could produce it in-house appropriately, that was approved, but the price change was not.”) (emphasis added). According to Aeroteam, because of the court’s misstatements, we must reverse its decision.

We disagree with Aeroteam. Certainly, to prove a claim for constructive change, a contractor need not show that the government authorized a change to the contract price. Rather, it need only show that the government ordered it (expressly or impliedly) to perform work beyond the contract requirements. See Bell/Heery, 739 F.3d at 1335 (citing Redland, 97 Fed. Cl. at 755–56). To the extent the Claims Court suggested otherwise, that was erroneous. Regardless, any such error was harmless. As explained above, the court carefully evaluated the evidence and determined that Aeroteam chose to manufacture the running gears itself, with no express or implied order from the Air Force. See J.A. 4 (833:23–834:3) (“[T]o demonstrate a constructive change, [a] plaintiff has to show . . . that the additional work was ordered expressly or impliedly by the government.”); J.A. 7 (846:11–13) (“The termination that [Aeroteam] exercised toward[] PDI was, again, a choice that [it] made.”) (emphasis added); J.A. 8 (849:8) (Aeroteam “offered to pull [the manufacturing] in-house.”) (emphasis added). Thus, the court’s possible suggestion of an additional requirement for constructive change did not affect the outcome of the case. See Valles v. Dep’t of State, 17 F.4th 149, 152 (Fed. Cir. 2021) (“As an appellate court, we are obligated to apply the rule of harmless error, examining the record ‘without regard to errors or defects which do not affect the substantial rights of the parties.’” (quoting 28 U.S.C. § 2111)).

Accordingly, we affirm the Claims Court’s determination that the Air Force was not liable for constructively changing the contract.

II

We next turn to Aeroteam’s argument regarding its cardinal change claim. To demonstrate a cardinal change, a contractor must show that the “government effect[ed] an alteration in the work” that “effectively require[d] the contractor to perform duties materially different from those

originally bargained for.” Krygoski Constr. Co. v. United States, 94 F.3d 1537, 1543 (Fed. Cir. 1996) (emphasis added) (quoting AT & T Commc’ns, Inc. v. WilTel, Inc., 1 F.3d 1201, 1205 (Fed. Cir. 1993)). “By definition . . . a cardinal change is so profound that it is not redressable under the contract, and thus renders the government in breach.” Id.

Aeroteam argues that the Air Force was liable for making a cardinal change to the contract. In support of its argument, Aeroteam again asserts that the Air Force ordered it to manufacture the running gears in-house. The government responds that Aeroteam’s cardinal change claim fails for the same reason that its constructive change claim fails: Aeroteam chose to manufacture the running gears. The Air Force did not order it to do so.

We agree with the government. As explained above, the evidence showed that Aeroteam chose to manufacture the running gears; the Air Force did not “effect an alteration” in Aeroteam’s work. See J.A. 7 (846:11–13); Krygoski, 94 F.3d at 1543 (emphasis added) (quoting AT & T, 1 F.3d at 1205). Accordingly, we affirm the Claims Court’s determination that the Air Force was not liable for making a cardinal change to the contract.

III

Finally, we turn to Aeroteam’s argument regarding its commercial impracticability claim. To prove commercial impracticability, a contractor must show that “because of unforeseen events, [the contract] can be performed only at an excessive and unreasonable cost” or “all means of performance are commercially senseless.” Raytheon Co. v. White, 305 F.3d 1354, 1367 (Fed. Cir. 2002) (citations and internal quotation marks omitted).

Because we determine that the Air Force did not “effect an alteration” in Aeroteam’s work, we need not reach the question whether any alteration was “materially different from those [that Aeroteam] originally bargained for.” Krygoski, 94 F.3d at 1543 (emphasis added) (quoting AT & T, 1 F.3d at 1205).

Aeroteam argues that it would have been commercially impracticable for it to perform the contract. According to Aeroteam, PDI could “no longer produce” the running gears in light of its financial difficulties. Appellant’s Br. 8. In support of its argument, Aeroteam emphasizes that PDI’s products were “plagu[ed]” with quality control issues, making it doubtful that it could complete the manufacturing order. Id. The government responds that PDI could have continued to manufacture the running gears. Specifically, the government contends that PDI did not decline to manufacture the running gears after facing financial difficulties. Rather, it merely raised the price per unit. The government adds that Aeroteam could have paid that higher price but chose not to for its own financial reasons. We agree with the government. After considering the evidence, the Claims Court found that Aeroteam could have continued to buy the running gears from PDI. J.A. 5 (838:14–16) (“[T]he evidence does not support that at the higher price, PDI would not have continued to supply the product.”). The court acknowledged that PDI faced financial difficulties. It explained, however, that those difficulties caused PDI to raise the price of its running gears, not to stop producing them altogether. J.A. 7 (845:1–7). The court further emphasized that Aeroteam could have bought the running gears for the higher price but chose not to do so. J.A. 7 (845:8–10). Finally, the court found that Aeroteam failed to provide evidence “document[ing]” that the higher price was excessive. J.A. 7 (845:14–16). Aeroteam points to no clear error in the court’s factual findings. Rather, it effectively asks us to reweigh the evidence and hold in its favor. We decline to do so.

The Claims Court did not make a conclusive finding regarding the amount that PDI charged Aeroteam after facing financial difficulties. PDI charged other parties up to $38,000. J.A. 1861 (341:6–20).

Aeroteam further argues that the Claims Court misstated the law on firm-fixed-price contracts. According to Aeroteam, the court “seem[ed] to hold” that a contractor entering into a firm-fixed-price contract may not raise a claim for commercial impracticability. Appellant’s Br. 26–27.

We disagree with Aeroteam’s reading of the court’s decision. The court did not suggest that Aeroteam was barred from raising a commercial impracticability claim. Rather, it stated that certain types of changes to Aeroteam’s firmfixed-priced contracts were not necessarily compensable, including, for example, an increase in the market price of running gears. J.A. 5 (837:1–5) (“A finding of impracticability excuses a party from performing unless the party has assumed the risk of the event.”) (emphasis added). As the court explained, that was “part of the risk” that Aeroteam assumed in entering a firm-fixed-price contract. See J.A. 5 (837:23–838:6); J.A. 7 (846:13–15); Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1295 (Fed. Cir. 2002) (“The normal risk of a fixed price contract is that the market price will change.” (quoting N. Ind. Pub. Serv. Co. v. Carbon County Coal Co., 799 F.2d 265, 275 (7th Cir. 1986))). Accordingly, we affirm the court’s determination that it was not impracticable for Aeroteam to perform the contract.

Although the Claims Court initially stated that it “guess[ed]” the higher price made PDI an “unavailable source,” it immediately qualified that statement by emphasizing that “it was also a matter of choice on the part of [Aeroteam] not to pay the higher price.” J.A. 7 (845:8–10) (emphasis added).

In summary, the Claims Court did not clearly err in denying Aeroteam’s claims for constructive change, cardinal change, or commercial impracticability.

CONCLUSION

We have considered Aeroteam’s remaining arguments but find them unpersuasive. For the foregoing reasons, the decision of the Claims Court is affirmed.

AFFIRMED

This is a verbatim capture of the text layer of the court's own document in U.S. Aeroteam, Inc. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the Court of Federal Claims

Also Affirmed

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.