No. 2024-1134

Sheffield Korte Joint Venture v. Sec'y of the Army

May 22, 2025opinionAppeal from the ASBCA
AffirmedContract disputeNonprecedentialContractor appealed

Disposition

AFFIRMED

Affirmed. Read from the standalone disposition line the opinion closes on. The court left the decision below standing. That is a win for whoever prevailed below, which is the appellee.

Key Facts

Appellant
Sheffield Korte Joint Venture
Appellee
Secretary of the Army
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2024-1134
Decided
May 22, 2025

From the opinion's own decided line.

Matter
Contract dispute
Panel
MOORE, CHEN, CUNNINGHAM
Opinion by
MOORE

Appealed From

The Armed Services Board of Contract Appeals, the Contract Disputes Act board for the defense agencies and NASA.

Appeal from the Armed Services Board of Contract Ap peals in Nos. 62972, 62973, Administrative Judge J. Reid Prouty, Administrative Judge Richard Shackleford, Ad ministrative Judge Stephanie Cates-Harman

Counsel

For the appellant
MICHAEL WILSON
UB Greensfelder, LLP
Saint Louis, MO
For the appellee
BRYAN MICHAEL BYRD
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion6 pages, 9,079 characters, read from the court's own documentDecided May 22, 2025 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelMOORE, CHEN, CUNNINGHAMOpinion byMOORENonprecedentialAffirmed
Appealed fromArmed Services Board of Contract Ap peals62972, 62973Judge J. Reid ProutyThe opinion states: Appeal from the Armed Services Board of Contract Ap peals in Nos. 62972, 62973, Administrative Judge J. Reid Prouty, Administrative Judge Richard Shackleford, Ad ministrative Judge Stephanie Cates-Harman
The opinion closes: AFFIRMED(the standalone disposition line)

Authorities cited

2 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Tucker Act and the Judicial Code1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

7 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 7 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

SHEFFIELD KORTE JOINT VENTURE,

Appellant

v.

SECRETARY OF THE ARMY,

Appellee

2024-1134

Appeal from the Armed Services Board of Contract Ap-

peals in Nos. 62972, 62973, Administrative Judge J. Reid

Prouty, Administrative Judge Richard Shackleford, Ad-

ministrative Judge Stephanie Cates-Harman.

Decided: May 22, 2025

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
MICHAEL WILSON
UB Greensfelder, LLP
Saint Louis, MO
As the opinion writes it

MICHAEL WILSON, UB Greensfelder, LLP, Saint Louis, MO, argued for appellant.

For the appellee
BRYAN MICHAEL BYRD
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

BRYAN MICHAEL BYRD, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, STEVEN JOHN GILLINGHAM, PATRICIA M. MCCARTHY.

BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

Also represented by BRIAN M.

MICHAEL WILSON, UB Greensfelder, LLP, Saint Louis, MO, argued for appellant.

BRYAN MICHAEL BYRD, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, STEVEN J OHN G ILLINGHAM , P ATRICIA M. MCCARTHY .

Before MOORE, Chief Judge, CHEN and CUNNINGHAM,

Circuit Judges.

MOORE, Chief Judge.

Sheffield Korte Joint Venture (Sheffield) appeals from a summary judgment decision of the Armed Services Board of Contract Appeals (Board), which denied Sheffield’s request for an equitable adjustment and granted the U.S. Army Corps of Engineers’ (Corps) request for repayment of improperly issued funds. We affirm.

BACKGROUND

The Corps solicited bids for a fixed-price design-build contract to construct an Army Reserve Center in Charles County, Maryland. J.A 2 ¶¶ 1–2. The solicitation documents contained a specification describing general project requirements and conceptual drawings depicting major features of the project. J.A. 1825–59 (specification); J.A. 1441 (drawing). One major feature was a stormwater management system. J.A. 1441 (denoted by keynote 30).

Sheffield submitted a bid for the project that included a design for a centralized stormwater management system. See J.A. 3278–81. In August 2015, the Corps accepted the bid and awarded Sheffield the contract for $21,427,802. J.A. 2 ¶¶ 1–2. In September 2016, Sheffield sent the Corps a letter explaining the stormwater management system depicted in the solicitation documents differed from that required by the State of Maryland. J.A. 3278–81. Sheffield noted the conceptual drawings

A centralized system collects stormwater in a single feature like a pond, whereas a decentralized system uses multiple, small-scale features to control stormwater and is intended to replicate natural hydrology. J.A. 3294–

95.

included a centralized system but that local requirements mandated a decentralized system. Id. The Corps disagreed that the requirements in the solicitation documents differed from those imposed by local officials. J.A. 3282. In April 2017, Sheffield submitted a request for an equitable adjustment of $1.8 million based on changes to the stormwater management system. J.A. 3292–301. The Corps denied Sheffield’s request. J.A. 3370–71 (non-final decision). The Corps did, however, issue a series of unilateral contract modifications increasing the contract price by $418,406 to compensate Sheffield for expenses incurred in meeting local requirements. J.A. 7–14 ¶¶ 22–43.

In November 2020, Sheffield certified its request for an equitable adjustment. J.A. 3402. In April 2021, the Corps denied Sheffield’s request and asked Sheffield to repay the $418,406, which the Corps claimed was issued in error. J.A. 3403–37 (final decision). Sheffield appealed to the Board. On summary judgment, the Board denied Sheffield’s request for an equitable adjustment and ordered it to repay the Corps. J.A 16–21 (citing United States v. Spearin, 248 U.S. 132 (1918)). Central to the Board’s analysis was its conclusion the Spearin implied warranty does not apply to the contract between Sheffield and the Corps. Sheffield appeals. We have jurisdiction pursuant to 41 U.S.C. § 7107(a)(1)(A) and 28 U.S.C. § 1295(a)(10).

DISCUSSION

We review the Board’s legal conclusions de novo. Kellogg Brown & Root Servs., Inc. v. Sec’y of the Army, 973 F.3d 1366, 1370 (Fed. Cir. 2020). The Board’s decision to grant or deny summary judgment is a legal conclusion.

Cessna Aircraft Co. v. Dalton, 126 F.3d 1442, 1446 (Fed. Cir. 1997). So too is its interpretation of contracts, Triple Canopy, Inc. v. Sec’y of the Air Force, 14 F.4th 1332, 1338 (Fed. Cir. 2021), including deciding whether the Spearin implied warranty applies, Blake Const. Co. v. United States, 987 F.2d 743, 746 (Fed. Cir. 1993).

When the government provides a contractor with a defective design specification, the government is deemed to have breached the Spearin implied warranty that satisfactory contract performance will result from adherence to the specification. Rick’s Mushroom Serv., Inc. v. United States, 521 F.3d 1338, 1344–45 (Fed. Cir. 2008); see also Spearin, 248 U.S. at 135–36. Such a breach entitles the contractor to recover all costs proximately flowing from the breach. Rick’s, 521 F.3d at 1344–45. The Spearin implied warranty, however, does not attach to performance specifications. Id. at 1344. Unlike design specifications, which “explicitly state how the contract is to be performed and permit no deviations,” performance specifications “specify the results to be obtained, and leave it to the contractor to determine how to achieve those results.” Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1582 (Fed. Cir. 1987). A key factor in distinguishing a design specification from a performance specification is the amount of discretion given to the contractor in implementation. Blake, 987 F.2d at 746–47.

Sheffield argues the Board legally erred by concluding the Spearin implied warranty does not apply to its contract with the Corps. Appellant Br. 39–75. Specifically, Sheffield argues the solicitation documents (i.e., the specification and conceptual drawings) show a centralized stormwater management system is a design requirement to which the Spearin implied warranty applies. We do not agree.

While the conceptual drawings depict a “stormwater management facility” in the northern portion of the site, they do not specify the type of stormwater management system. J.A. 1441; J.A. 1511. The drawings do, however, state the stormwater management system depicted is only an approximation, and the contractor is responsible for determining the “actual size and location” of the system. J.A. 1441 (keynote 30); J.A. 1511 (keynote 30). Regardless, even if these drawings appear to depict a centralized

system, the specification makes clear it is not a design requirement.

The specification shows Sheffield was required to design the stormwater management system in accordance with local requirements, was responsible for obtaining all necessary permits, and had discretion to refine the conceptual design accordingly. See, e.g., J.A. 1831 §§ 1.2.4.2–3, 1833 § 1.3.1, 1852 § 3.1.8.2 The specification also provides that federal, state, and local regulations are “considered the minimum design criteria” for designing “stormwater management systems” and that “[l]ow impact development strategies” can be used to restore “the natural hydrologic functions of a site.” J.A. 1859 § 3.4.5. Moreover, the specification incorporates the 2010 Maryland Stormwater Management Guidelines, J.A. 1843 § 2.2.1, which explain environmental site design for stormwater management is required to the “maximum extent practicable,” J.A. 747– 62. Because Sheffield had significant discretion to design and build the stormwater management system in accordance with local regulations and the specification did not require a centralized stormwater management system, this is a performance specification to which the Spearin implied warranty does not apply. Stuyvesant, 834 F.2d at 1582.

2The contract between the parties also includes a “permits and responsibilities” clause that makes Sheffield “responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.” J.A. 1692.

Environmental site design is a design for decentralized stormwater management systems. J.A. 754 ¶ 14; J.A. 3278–81.

CONCLUSION

We have considered Sheffield’s remaining arguments and find them without merit. For the foregoing reasons, we affirm.

AFFIRMED

This is a verbatim capture of the text layer of the court's own document in Sheffield Korte Joint Venture v. Sec'y of the Army. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the ASBCA

Also Affirmed

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.