CBCA 3693

Yasmin Saighi

Mar 25, 2015Judge DrummondGENERAL SERVICES ADMINISTRATION
DecisionDenied

Key Facts

Appellant
Yasmin Saighi
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Drummond
Case number
CBCA 3693
Decided
Mar 25, 2015The decision states Mar 25, 2015 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Denied
This appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Jurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions.

Appearances

For the appellant (pro se)
Yasmin Saighi
Tulsa, OK
For the respondent
Jenny M. Matte
Office of Regional Counsel, General Services Administration
Atlanta, GA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision7 pages, 14,503 characters, read from the Board's own documentDecided Mar 25, 2015 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: March 25, 2015

CBCA 3693

YASMIN SAIGHI,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

Yasmin Saighi, pro se, Tulsa, OK.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jenny M. Matte, Office of Regional Counsel, General Services Administration, Atlanta, GA, counsel for Respondent.

Before Board Judges SOMERS, McCANN, and DRUMMOND.

DRUMMOND, Board Judge.

This appeal arises out of the purchase of a boat by Yasmin Saighi at an online auction conducted by the General Services Administration (GSA). GSA and Ms. Saighi have filed motions for summary relief. Ms. Saighi has also moved to strike GSA’s denial that an agency relationship existed between GSA and Ed Weilbacher, general manager of Kaskaskia Regional Port District, Evansville, Illinois. We grant GSA’s motion and deny Ms. Saighi’s motions.

Background

In May 2013, GSA conducted an internet auction for the sale of a fire/patrol boat named the “M/V Blankenship” (boat). The boat information, including photographs, was shown on the website. The boat description estimated that the boat was manufactured in 1987. It stated, inter alia, that the boat had “twin draft V6 - 92TA Detroit diesel engines . . . [which were] rebuilt in April 1998 [and a] Kubota V2038 diesel engine, 5 cyl, 46 BHP [and] . . . needs new batteries.” The description included the warning that “repairs may be required. Parts may be missing. Deficiencies, when known, have been indicated in the property description. However, absence of any indicated deficiencies does not mean that none exits.” The description also included a statement, appearing in all capital letters, warning bidders that GSA did not warrant the condition of the boat.

The boat was docked at the Kaskaskia Regional Port District marina in Evansville, Illinois, and was available for bid only by persons who accepted the terms and conditions of sale which were posted on the website. Ms. Saighi inspected the boat prior to the auction and did not advise GSA as to any problems with the boat. She also agreed to the terms and conditions of the sale, including the following paragraphs: Inspection of Property

Bidders agree to physically inspect the property upon which they bid or thereby waive the opportunity to conduct a physical inspection. In waiving their inspection rights, bidders bear the risk for any gross omissions regarding the functionality of items, failures to cite major missing parts and/or restrictions with regards to usage that would have been revealed by physical inspection. There are times when access to property may be limited due to property being located in a restricted area. GSA will do all that it can to ensure that photos and detailed descriptions are provided in these instances.

During an inspection at a government facility, actions taken by bidders are at their own risk. The U.S. Government will not be liable for any or all debts, judgments, costs, demands, suits, actions, or claims of any nature arising from or incident to their inspection at the Government facility, including any injuries that a bidder incurs due to their own actions or neglect on during [sic] their visit to a Government facility.

Reporting Discrepancies/Hazardous Materials Prospective purchasers are asked to inform the sales office of any discrepancies in the property descriptions discovered while inspecting the property and of any lots in this sale that contain hazardous material/waste not indicated in the property descriptions.

Condition of Property

The following replaces Clause 2 of the General Terms and Conditions of the Standard Form (SF) 114C: Condition of property is not warranted.

Deficiencies, when known, have been indicated in the property descriptions.

However, absence of any indicated deficiencies does not mean that none exists. Therefore, the bidder should ascertain the condition of the item through physical inspection. Please also reference the Inspection of Property clause.

Description Warranty & Refunds

The Government warrants to the original purchaser that the property listed in the GSAAuctions.gov website will conform to its written description. Features, characteristics, deficiencies, etc. not addressed in the description are excluded from this warranty. GSA further cautions bidders that GSA’s written description represents GSA’s best effort to describe the item based on the information provided to it by the owning agency. Therefore, gross omissions regarding the functionality of items, failures to cite major missing parts and/or restrictions with regards to usage may occur.

The Government does not warrant the merchantability of the property or its purpose. The purchaser is not entitled to any payment for loss of profit or any other money damages - special, direct, indirect, or consequential.

Refunds Claim Procedures

Please be advised that refunds are not a frequent practice of GSA Auctions.

A request for refund must be substantiated in writing to the Contracting Officer for issues regarding misdescribed property, missing property and voluntary defaults within 15 calendar days from the date of payment.

Refund Amount

The refund is limited to the purchase price of the misdescribed property.

Claims of Misdescription

If items have been awarded but not paid for and the successful bidder feels that the property is misdescribed, he/she must follow these procedures: A written claim needs to be submitted to the Sales Contracting Officer within 15 calendar days from the date of award requesting release of contractual obligation for reasons satisfying that of a misdescription. No verbal contact with the custodian or the Sales Contracting Officer or any other federal official will constitute a notice of misdescription.

GSA awarded the contract for the boat to Ms. Saighi on May 30, 2013, noting that the bid price was $30,056. Ms. Saighi paid for the boat and took possession of it on June 6, 2013. Ms. Saighi claims that she expended $2200 in repairs. The repairs include installing two new marine batteries and repairing a broken window and door.

The first notification that Ms. Saighi was not satisfied with the condition of the boat is found in her email message dated October 27, 2013, sent to the contracting officer. Ms. Saighi complained that GSA had failed to disclose important information regarding the boat. Ms. Saighi stated that she had recently learned from local residents that the boat partially sank a few years before the sale. She stated further that both engines needed to be overhauled at a cost of approximately $96,000.

By letter dated November 19, 2013, the contracting officer responded to Ms. Saighi’s email message dated October 27, 2013. The contracting officer stated that she had contacted Ed Weilbacher, the custodian and he confirmed the . . . [boat] was in sound condition and afloat at dock for 2 years prior to this sale. The dip sticks were checked and there was no water in the engines. The . . . [boat] was in the state of remodeling that was never completed. The custodian also confirmed that all bidders were made aware of the condition and he made no assurances or guaurantees that the engines ran.

On June 29, 2013, you authorized your husband . . . to remove the . . . boat on your behalf . . . in early September. The individual that you hired for towing did not have a big enough engine, and after going up river for a short distance, the . . . [boat] was returned to the deck barge dock.

The record does not indicate the condition of the boat upon its return.

The contracting officer stated further that GSA cautioned bidders that the “written description represents GSA’s best effort to describe the item based on the information provided to it by the owning agency. Therefore, gross omissions regarding the functionality of items, failures to cite major missing parts and/or restrictions with regards to usage may occur.”

The contracting officer continued by stating that the “Government does not warrant the merchantability of the property or its purpose. The purchaser is not entitled to any payment for loss of profit or any other money damages - special, direct, indirect, or consequential.”

On December 1, 2013, Ms. Saighi repeated her written complaint that the boat partially sank before the auction. She alleged that GSA knew or should have known about the earlier sinking and GSA should have advised potential bidders of the sinking within the sale description. Ms. Saighi requested that GSA refund the “full purchase price and money invested [presumably the $2200 for repairs].” Alternatively, she requested that GSA “refund 50% of the purchase price.” The contracting officer responsible for this contract has stated in her affidavit that neither she nor any other GSA employee had knowledge that the boat sank before the sale. Likewise, Mr. Weilbacher has stated in his affidavit that he has no knowledge or information of the boat sinking prior to the sale.

On December 11, 2013, the contracting officer issued a formal decision denying Ms. Saighi’s claim. The decision referenced the terms and conditions above and concluded that the boat was not misdescribed in the sales information, the condition was not guaranteed, and the claim was not timely submitted. The contracting officer concluded by advising Ms. Saighi about her appeal rights.

On appeal, Ms. Saighi alleges breach of contract and fraud due to misdescription and seeks $30,056 in exchange for the boat, reimbursement of the $2200 expended for repairs, and punitive damages exceeding $50,000. Ms. Saighi alleges that Mr. Weilbacher’s affidavit statement denying any prior knowledge of the boat sinking is false and has offered documents and sworn statements as support. The Board finds that the documents and sworn statements submitted by Ms. Saighi fail to show conclusively that Mr. Weilbacher’s affidavit statements are false. The Board also finds that Ms. Saighi’s evidence fails to show that Mr. Weilbacher was acting as an agent of GSA.

Discussion

GSA has moved for summary relief, asserting that, as a matter of law, the boat was not misdescribed and Ms. Saighi is, in any event, not entitled to relief because she failed to comply with the terms and conditions of the auction. Ms. Saighi has filed a cross motion. She alleges for the first time that the contract is voidable based on agency and joint venture theories. She additionally alleges that she is entitled to punitive damages and attorney fees. Ms. Saighi has additionally moved to strike GSA’s statements denying that an agency relationship existed between GSA and the State of Illinois and that the State of Illinois failed to disclose to GSA that the boat sank prior to the sale and that both engines had been submerged. GSA disputes Ms. Saighi’s allegations and opposes the motion to strike. GSA argues that the Board lacks jurisdiction to consider the agency and joint venture allegations, as they were never presented to the contracting officer.

Summary relief is appropriate when the moving party is entitled to judgment as a matter of law, based on undisputed material facts. The moving party shoulders the burden of proving that no genuine issues of material fact exists. Patick C. Sullivan v. General Services Administration, CBCA 936, 08-1 BCA ¶ 33,820. The nonmoving party is then required to rebut the motion by articulating facts that show there is a genuine issue for trial. Celotex Corp.v. Catrett, 477 U.S. 317, 324 (1986).

The terms and conditions of the auction in which Ms. Saighi purchased the boat preclude the relief she seeks. First, the “Description Warranty” paragraph of the terms and conditions provides that the GSA’s only warranty is that the property listed on the website will conform to its description. Ms. Saighi does not allege that the boat did not conform to its written description.

Second, the “Oral Statements and Modifications” paragraph provides that “[a]ny oral statement or representation by any representative of the Government, changing or supplementing the offering or contract or any condition thereof, is unauthorized and shall confer no right upon the bidder or purchaser.” Statements by third parties, if made, were oral and therefore confer no right on the purchaser. Gaven L. Rouse v. General Services Administration, GSBCA 15993, 03-1 BCA ¶ 32,210.

Third, even if those purported oral statements did confer on Ms. Saighi a right to recover for a misdescription, the “Description Warranty” and “Refund Claim” paragraphs provide that once an item has been moved by the purchaser, a refund is available only if the purchaser fulfills three requirements. She must submit a written notice of misdescription to the contracting officer within fifteen days of the date of award or payment, maintain the property in the purchased condition until it is returned, and return the property to a location specified by the contracting officer. Ms. Saighi did not fulfill any of these requirements. Fourth, the “Description Warranty” and “Refund Amount” paragraphs limit recovery in the event of a misdescription to a refund of the purchase price. Payment for repairs is not allowed. William W. Caswell v. General Services Administration, CBCA 479, 07-2 BCA ¶ 33,679; John A. Glasure v. General Services Administration, GSBCA 16046, 03-2 BCA ¶ 32,284; Dan Parish v. General Services Administration, GSBCA 16025, 03-1 BCA ¶ 32,211; Bob’s Auto Sales v. General Services Administration, GSBCA 14447, 98-1 BCA ¶ 29,647; Garrett J. Veenstra, GSBCA 7251, 85-2 BCA ¶ 18,127, at 90,983 (Board cannot reform contract to give purchaser of boat at auction the different remedy of keeping the vessel and receiving reimbursement for repairs).

This Board has no subject matter jurisdiction to award punitive damages. See Schrager Auction Galleries, Ltd. v. Department of the Treasury, GSBCA 15658-TD, 02-1 BCA ¶ 31,710 (2001). There also is no basis for this Board to decide appellant’s allegations that the contract is voidable based on agency and joint venture theories, because these allegations involve different operative facts from those presented to the contracting officer. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010). These claims must be first presented to the contracting officer. Accordingly, Ms. Saighi’s motion to strike is denied.

Decision

The Board grants GSA’s motion for summary relief and denies Ms. Saighi’s motion for summary relief. This appeal is DENIED.

_______________________

JEROME M. DRUMMOND

Board Judge

We concur:

JERI K. SOMERS

Board Judge

R. ANTHONY McCANN

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Yasmin Saighi, CBCA 3693. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.