CBCA 423-R

Hook Construction, Inc.

Jan 19, 2007Judge ParkerGENERAL SERVICES ADMINISTRATION
Not published in the listingRuled on a motion

Key Facts

Appellant
Hook Construction, Inc.
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Parker
Case number
CBCA 423-R
Decided
Jan 19, 2007The decision states Jan 19, 2007 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Ruled on a motion
The motion for reconsideration is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Procedure and sanctions

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions.

Appearances

For the appellant
Kenneth R. Hook
Hook Construction, Inc.
Solon, IA
For the respondent
Mark R. Warnick
Office of Regional Counsel, General Services Administration
Kansas City, MO
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision3 pages, 4,992 characters, read from the Board's own documentDecided Jan 19, 2007 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

MOTION FOR RECONSIDERATION DENIED: January 19, 2007

CBCA 423-R

HOOK CONSTRUCTION, INC.,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Kenneth R. Hook, Vice President of Hook Construction, Inc., Solon, IA, appearing for Appellant.

Mark R. Warnick, Office of Regional Counsel, General Services Administration, Kansas City, MO, counsel for Respondent.

Before Board Judges PARKER, DEGRAFF, and GOODMAN.

PARKER, Board Judge.

Hook Construction, Inc. (Hook) moves the Board to reconsider its decision denying Hook’s claim for extra work performed in connection with the installation of wall covering at the United States Courthouse in Cedar Rapids, Iowa. Hook Construction, Inc. v. General Services Administration, GSBCA 16756, 06-2 BCA ¶ 33,404. We deny the motion.

Background

Eleven months after Hook installed wall covering in a judge’s office, the General Services Administration (GSA) discovered that the covering was delaminating at some of the seams and promptly notified Hook of the problem. Hook replaced the defective wall covering and submitted an invoice that included the amount of $2209.75 for the work. GSA 2 CBCA 423-R

determined that the repair was covered under the contract’s warranty provision, rejecting Hook’s argument that the delamination was caused by water damage that had occurred after installation.

On appeal, we agreed with GSA that defective workmanship, rather than water damage, was likely the cause of the delamination: As to the first issue, we find that GSA has shown by a preponderance of the evidence that a defect in workmanship was the most probable cause of the wall covering becoming delaminated. The contract required Hook to “examine the substrates” for “conditions affecting performance of the work” and to “proceed with installation only after unsatisfactory conditions have been corrected.” Hook was also required to “prepare substrates to achieve a smooth, dry, clean, structurally sound surface free of flaking, unsound coatings, cracks, and defects.” When the wall covering delaminated within the one-year warranty period, the Government’s inspection showed no water leakage or other condition that had changed between the time the wall covering was installed and the time it delaminated. Both parties agreed that the painted plaster surface on which the wall covering was installed was pulling away from the wall, causing the wall covering to separate at the seams.

GSA has shown that the most likely cause of the delamination was Hook’s failure to comply with the contract’s requirement to correct any unsatisfactory conditions before proceeding with the work. Hook’s acknowledgment that it did not strip off all of the old paint because “that’d be costs that the GSA would have to pay” demonstrates the company’s misunderstanding of the contract’s requirements. It was Hook’s responsibility to examine the pre-existing conditions and make certain that any unsatisfactory conditions were corrected prior to installation of the wall covering.

06-2 BCA at 165,624.

Discussion

Hook seeks to reargue the issue of whether the delamination of the wall covering was caused by water damage, rather than as a result of a defect in workmanship. In support, Hook maintains that GSA was aware of cracks in the wall prior to installation of the wall covering and that, recently, the carpet in the judge’s office was replaced due to a roof leak. In response, GSA points out that the roof leak, which occurred more than a year after Hook repaired the wall covering, was “due to structural damage caused to the courthouse roof

3 CBCA 423-R

during tornadic activity during the summer of 2005 and the negligence of a roofing contractor hired by GSA to make interim repairs to the courthouse roof.” Respondent’s Suggestions in Opposition to Appellant’s Motion for Reconsideration.

Hook’s argument for reconsideration based on the existence of cracks in the wall prior to initial installation of the wall covering merely reargues points previously made, which were considered and rejected by the Board. Arguments previously made and considered are not sufficient grounds for granting reconsideration. Long Lane Limited Partnership v. General Services Administration, GSBCA 15334-R, 04-2 BCA ¶ 32,751, affd, 159 Fed. Appx. 189 (Fed Cir. 2005). Hook’s information that the judge’s carpet was damaged by water in 2005 is similarly unpersuasive. A leak in the roof that occurred more than a year after the wall covering was repaired does not prove that the previous damage had been caused by water, especially considering that an investigation performed at the time of the delamination concluded that no water damage had occurred. GSA’s explanation that the subsequent water damage was caused by a tornado demonstrates this point perfectly.

Decision

The motion for reconsideration is DENIED.

_____________________

ROBERT W. PARKER

Board Judge

We concur:

MARTHA H. DEGRAFF

Board Judge

ALLAN H. GOODMAN

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Hook Construction, Inc., CBCA 423-R. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.