CBCA 5692, 5955

Eagle Peak Rock & Paving, Inc.

May 15, 2019Judge RussellDEPARTMENT OF TRANSPORTATION
DecisionRuled on a motion

Key Facts

Appellant
Eagle Peak Rock & Paving, Inc.
Respondent agency
DEPARTMENT OF TRANSPORTATION
Judge
Russell
Case number
CBCA 5692, 5955This cell names 2 dockets: 5692, 5955.
Decided
May 15, 2019The decision states May 15, 2019 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Varela, Lee, Metz & Guarino, LLP
Outcome
Ruled on a motion
Appellant's motion for summary judgment is DENIED, and respondent's motion for summary relief is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Termination for defaultDelay, suspension and accelerationProcedure and sanctions

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Bennett J. Lee and Stephen L. Pessagno
Varela, Lee, Metz & Guarino, LLP
San Francisco, CA
For the appellant
David B. Wonderlick
Varela, Lee, Metz & Guarino, LLP
Tysons Corner, VA
For the respondent
Rayann L. Speakman and Western Federal Lands Highway
Division, Federal Highway Administration, Department of Transportation
Vancouver, WA
For the respondent
Milton Hsieh and Eastern Federal Lands Highway
Division, Federal Highway Administration, Department of Transportation
Sterling, VA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 7,845 characters, read from the Board's own documentDecided May 15, 2019 on its own faceRespondent DEPARTMENT OF TRANSPORTATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. 2 open at a publisher or in this app; the rest are shown without a link because no published page for them was confirmed.

Federal Acquisition Regulation1
Agency FAR supplements1
Decisions of other forums1
ASBCA No. 17374

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

4 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 3 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

APPELLANT’S MOTION FOR SUMMARY JUDGMENT DENIED;

RESPONDENT’S MOTION FOR SUMMARY RELIEF DENIED1:

May 15, 2019

CBCA 5692, 5955

EAGLE PEAK ROCK & PAVING, INC.,

Appellant,

v.

DEPARTMENT OF TRANSPORTATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Bennett J. Lee and Stephen L. Pessagno of Varela, Lee, Metz & Guarino, LLP, San Francisco, CA; and David B. Wonderlick of Varela, Lee, Metz & Guarino, LLP, Tysons Corner, VA, counsel for Appellant.

Rayann L. Speakman, Western Federal Lands Highway Division, Federal Highway Administration, Department of Transportation, Vancouver, WA; and Milton Hsieh, Eastern Federal Lands Highway Division, Federal Highway Administration, Department of Transportation, Sterling, VA, counsel for Respondent.

Before Board Judges KULLBERG, SULLIVAN, and RUSSELL.

RUSSELL, Board Judge.

These appeals arise out of a contract between Eagle Peak Rock & Paving, Inc. (Eagle Peak) and the Department of Transportation’s Federal Highway Administration (FHWA or agency) for the construction of various improvements along approximately 4.7 miles of road in Yellowstone National Park as well as improvements at nearby parking areas, trails and overlooks. Both parties have moved for summary judgment on Eagle Peak’s appeal of the FHWA’s decision terminating the contract for default, and FHWA has also moved for summary judgment on Eagle Peak’s claim challenging the agency’s withholding retainage.

1Both parties are moving for the same relief with appellant characterizing its motion as one for summary judgment and respondent characterizing its motion as one for summary relief. Since the appeals were filed, a revision in the Board’s rules renamed motions for summary relief as motions for summary judgment. 48 CFR 6101.8(f) (2018) (Rule 8(f)).

Discussion

A termination for default is “a drastic sanction which should be imposed (or sustained) only for good grounds and on solid evidence.” Paradise Pillow, Inc. v. General Services Administration, CBCA 3562, 15-1 BCA ¶ 36,153, at 176,441 (citing Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987)). A termination for default is a government claim, and the Government bears the burden of proof that its action was justified. Lisbon Contractors, 828 F. 2d at 765; Affiliated Western, Inc. v. Department of Veterans Affairs, CBCA 4078, 17-1 BCA ¶ 36,808, at 179,401.

Here, FHWA terminated Eagle Peak under the contract provision allowing for terminations “[i]f the contractor refuses or fails to prosecute . . . work [under the contract] or any separable part, with the diligence that will ensure its completion within the time specified in the contract including any extension, or fails to complete the work within this time.” 48 CFR 52.249-10 (1996). “A termination for default for failure to prosecute the work requires “a reasonable belief on the part of the contracting officer that there was ‘no reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance.”’ Lisbon Contractors, 828 F.2d at 765 (quoting RFI Shield-Rooms, ASBCA Nos. 17374, 17991, 77-2 BCA ¶ 12,714, at 61,735); see also Singleton Enterprises v. Department of Agriculture, CBCA 2136, 12-1 BCA ¶ 35,005, at 172,038 (citing McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1016 (Fed. Cir. 2003) (adopting this formulation as the controlling standard in default cases involving a failure to make sufficient progress)); Affiliated Western, Inc., 17-1 BCA ¶ 36,808, at 179,401. “A termination for failure to make progress usually occurs where the contractor has fallen so far behind schedule that timely completion becomes unlikely.” Affiliated Western, Inc., 17-1 BCA ¶ 36,808, at 179,401 (citations omitted). “The Government is not required to prove that it was impossible for the contractor to complete performance on time.” Id. Rather, a termination for default will be upheld where “a demonstrated lack of diligence indicates that [the Government] could not be assured of timely completion.” Discount Co. v. United States, 554 F.2d 435, 441 (1977); see also Global Construction, Inc. v. Department of Veterans Affairs, CBCA 1198, 10-1 BCA ¶ 34,363, at 169,699; Affiliated Western, Inc., 17-1 BCA ¶ 36,808, at 179,401.

Both parties have moved for summary disposition on Eagle Peak’s appeal challenging the default termination. As an initial matter, the parties dispute whether the contracting officer applied the correct standard in reaching her decision to terminate Eagle Peak’s contract - i.e., whether she had a reasonable belief that there was “no reasonable likelihood” that Eagle Peak could perform the construction services within the time remaining for contract performance. See Lisbon Contractors, 828 F.2d at 765. Relying on the contracting officer’s deposition testimony, Eagle Peak asserts that the contracting officer based her termination decision on whether there was “a reasonable likelihood” that Eagle Peak would not complete the construction project within the contract period of performance, as opposed to finding, as required, that there was “no reasonable likelihood” that the company could complete the project within the required deadline. For its part, FHWA asserts that, contrary to Eagle Peak’s argument, the contracting officer did, in fact, apply the appropriate standard for a default determination as evidenced by language in a letter sent by the contracting officer to Eagle Peak shortly after Eagle Peak was notified of the termination. In the letter, the contracting officer stated that she terminated Eagle Peak’s contract because she determined that there was “no reasonable likelihood” that Eagle Peak could meet the completion date in the contract.

From there, the disputed facts on the default termination claim are many. The parties dispute the sufficiency of the agency’s consideration of a number of factors as relates to the agency’s termination of the construction contract including but, not limited to, Eagle Peak’s work progress prior to the termination, proposed schedules, production rates and resources; tasks on the critical path and the impact, if any, of those tasks on project completion; who caused any delay and how long did it last; and the appropriate application of an agency specification for construction of roads. Further, Eagle Peak raises disputed facts relating to the agency’s withholding retainage. Specifically, Eagle Peak challenges the agency’s withholding of a certain percentage of progress payments based on Eagle Peak’s alleged failure to provide a contract-compliant project schedule to the agency within a timely manner.

The parties support their respective motions with references to Rule 4 documents including agency construction specifications, deposition transcripts including those of experts, and other evidence. “It is well settled that in order to obtain summary relief, a party must show that there are no material factual disputes[,] . . . and it is entitled to judgment as a matter of law.” DOT Construction, Inc. v. Department of Agriculture, CBCA 3966, 15-1 BCA ¶ 36,011, at 175,887; see also 6th and E Associates, LLC v. General Services Administration, CBCA 1802, 10-2 BCA ¶ 34,596, at 170,527. We find that there are unresolved disputed facts that preclude resolution of the two appeals by summary disposition. See AT&T Technical Services Company, Inc. v. Department of Veterans Affairs, CBCA 6171, slip op. at 4 (May 6, 2019) (denying parties’ cross-motions noting that the record was replete with conflicting evidence).

Decision

Appellant’s motion for summary judgment is DENIED, and respondent’s motion for summary relief is DENIED. The hearing in these appeals shall commence on May 29, 2019. Beverly M. Russell

BEVERLY M. RUSSELL

Board Judge

We concur:

H. Chuck Kullberg

Board Judge

Marian E. Sullivan

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Eagle Peak Rock & Paving, Inc., CBCA 5692, 5955. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.