Thorington Electrical and Construction Company
Thorington Electrical and Construction Company appealed a final decision denying its claim under Contract No. FA3300-06-C-0015, which the government moved to dismiss or for summary judgment. The Board granted the government's motion, resulting in a denial of the appeal.
Material Facts
- The Air Force awarded Contract No. FA3300-06-C-0015 to Thorington Electrical and Construction Company for a firm, fixed price of $3,433,290.
- The contract was for a 10-lane bowling center at Maxwell, AFB.
- On 14 February 2008, TECC submitted an invoice for $96,320.15, which was paid in full and included a release of claims.
- On 5 February 2009, TECC submitted a certified claim for $114,112.66 citing increased material costs.
- The contracting officer issued a final decision on 25 March 2009 denying the claim based on the release and the absence of an Economic Price Adjustment clause.
- TECC filed an appeal with the Board on 31 July 2009.
Parties
- Appellant
- Thorington Electrical and Construction Company
- Respondent Agency
- Air Force
- Contract Number
- FA3300-06-C-0015
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Northrop Grumman CorporationNo. 60510May 25, 2017
- Skanska USA Civil Southeast, Inc.No. 61141May 24, 2017
- Ahmad Azami Construction CompanyNo. 61003May 22, 2017
- Harris CorporationNo. 60732May 19, 2017
- Aldon Bookhardt Roofing Inc.No. 60989May 18, 2017
- Framaco-Epik-Metis JVNo. 60557, 60558, 60559, 60560May 18, 2017
Same Year
- C.E.M.E.S. S.p.A.No. 56253, 57355December 29, 2010
- Shaw Environmental, Inc.No. 57237December 16, 2010
- Thorington Electrical and Construction CompanyNo. 56997December 13, 2010
- Phoenix Management, Inc.No. 57234December 13, 2010
- Parsons Global Services, Inc.No. 56731December 3, 2010
- Kelly-Ryan, Inc.No. 57168November 29, 2010
Same Issue
- Bodell Construction CompanyNo. 63517-ADR, 63850-ADROctober 2, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- WSP USA Solutions Inc.No. 62674September 1, 2026
- Mvation Worldwide Inc.No. 64633August 18, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026