Thorington Electrical and Construction Company appealed for reimbursement of increased material costs under a firm fixed-price contract. The Board denied the appeal, ruling that the contractor bore the risk of cost fluctuations.

Material Facts

  • The government awarded Contract No. FA3300-05-C-0015 to the appellant on 30 September 2005 for the construction of a new entry control facility.
  • The contract was a firm fixed-price contract for the amount of $825,288.
  • The contract included various standard clauses by reference, including FAR 52.243-4, Changes.
  • The appellant submitted a certified claim for $764,813, which included a sub-claim for increased asphalt costs of $110,956.
  • The contracting officer determined that the contract did not contain the Economic Price Adjustment clause and offered a compromise settlement of $26,635.83, which the appellant did not accept.

Parties

Appellant
Thorington Electrical and Construction Company
Respondent Agency
Department of the Air Force
Contracting Agency
Department of the Air Force
Contract Number
FA3300-05-C-0015
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.