56711

Macro-Z Technology

August 18, 2014Judge James
DismissedCDA Jurisdiction

Macro-Z Technology appealed the deemed denial of its claim under Contract No. N44255-04-D-9122, which sought $5,434,297 for various damages. The Board dismissed the appeal due to lack of jurisdiction.

Material Facts

  • The contracting officer deemed Macro-Z Technology's claim of $5,434,297 denied.
  • The claim was based on alleged impact damages, delay damages, and proposal preparation costs.
  • The Board found that the claim lacked a sum certain for its pre-award elements.
  • Macro-Z Technology's motion for partial summary judgment focused on pre-award Navy conduct.

Parties

Appellant
Macro-Z Technology
Contract Number
N44255-04-D-9122
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.