Northrop Grumman Corporation
Northrop Grumman Corporation sought reconsideration of the Board’s decision denying its appeal on entitlement concerning the allowability of claimed PRB costs measured and assigned using DEFRA. The Board held that the motion repeated previously rejected arguments, established no Board error, and affirmed its prior decision.
Material Facts
- Northrop Grumman used DEFRA to measure and assign PRB costs.
- The claimed costs included unfunded prior year PRB costs.
- The government’s Disclosure Statement responses stated that disclosed practices were not thereby deemed proper, approved, or agreed to practices.
- The DCAA auditor was aware of Northrop Grumman’s use of DEFRA in the 1990s.
- The DCAA auditor did not question the methodology or related annual costs because Northrop Grumman was not claiming costs in excess of those allowed under FAS 106.
- Northrop Grumman asserted that the government’s awareness, communications, inaction, and the 2002 GAO Review supported its position.
Parties
- Appellant
- Northrop Grumman Corporation
- Respondent Agency
- Defense Contract Management Agency
- Contract Number
- N68936-05-C-0059
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Kellogg Brown & Root Services, Inc.No. 59357, 59358August 29, 2016
- GSC Construction, Inc.No. 59644, 59956, 60069, 60070, 60112, 60113June 21, 2016
- Access Personnel Services, Inc.No. 59900June 15, 2016
- CI², Inc.No. 59948June 6, 2016
- CI², Inc.No. 59948June 6, 2016
- CI², Inc.No. 59948June 6, 2016
Same Year
- Fluor Enterprises, Inc. and Fluor CorporationNo. 59367, 59697December 24, 2014
- The Boeing CompanyNo. 59216December 24, 2014
- Government Services Corp.No. 59654December 23, 2014
- Raytheon Missile SystemsNo. 59432December 23, 2014
- CAE USA, Inc.No. 58957December 23, 2014
- Metal Storm, Inc.No. 58901December 23, 2014
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026
- Raytheon Company and Raytheon Missile SystemsNo. 59435, 59436, 59437, 59438, 60056, 60057, 60058, 60059, 60060, 60061May 14, 2026
- IAP Worldwide Services, Inc.No. 62638, 63879May 6, 2026
- CACI International, Inc.No. 63663March 10, 2026