Raytheon Company
Raytheon Company challenged penalties and interest assessed on allegedly expressly unallowable costs included in corporate and divisional incurred cost proposals. The Board sustained the appeals concerning aircraft, M&A database, and specified consultant costs, denied the challenge to non-waiver of penalties on lobbying salary costs, dismissed withdrawn matters without prejudice, and remanded remaining quantum issues.
Material Facts
- The contract was identified as a Labor-Hour, Time-and-Materials, Services and Research and Development contract, with specified efforts performed on a Cost-Plus-Fixed-Fee basis for engineering services associated with the Patriot Weapon System.
- Raytheon submitted certified corporate and Integrated Defense Systems final indirect cost proposals for the relevant years.
- Raytheon had advance agreements addressing the allowability and withdrawal factors for aircraft fractional lease costs and later entered an advance agreement concerning Challenger 604 aircraft costs.
- Raytheon's 2004 corporate proposal included aircraft fractional lease costs without applying the applicable agreed withdrawal factor and included Challenger 604 costs using a placeholder recovery factor before the parties executed a later advance agreement.
- Raytheon's Washington Office performed both allowable and unallowable activities, and Raytheon used a ratio-based method to withdraw lobbying-related salary costs.
- The lobbying withdrawal calculation contained missing time records, proration errors, omissions, and an erroneous inclusion of executive hours that had been withdrawn elsewhere.
- Raytheon paid Icent for design and construction of an M&A Support Center Application intended for general planning and specific M&A purposes, but the project was terminated before completion and was never used in connection with an M&A target.
- Raytheon's consultant costs included fees for Stephen Stanvick and VADM J. Guy Reynolds, both of whom had consulting agreements and relevant experience.
- Stanvick's work was substantially technical and classified, and much of his work product was oral or could not be publicly disseminated or retained.
- Reynolds's invoices generally described his services, and credible testimony established that he prepared trip reports and generated written communications even though the 2005 reports were unavailable.
- DCAA audited the relevant incurred cost proposals and questioned costs as unallowable or expressly unallowable, after which DCMA contracting officers assessed penalties and interest.
Parties
- Appellant
- Raytheon Company
- Respondent Agency
- Defense Contract Management Agency
- Contracting Agency
- U.S. Army Aviation and Missile Command
- Contract Number
- W31P4Q-04-C-0020
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Pratt & Whitney, a division of Raytheon Technologies CompanyNo. 59222November 22, 2021
- Raytheon CompanyNo. 58212, 58753June 14, 2021
- Raytheon CompanyNo. 58841June 14, 2021
- Raytheon CompanyNo. 58842June 14, 2021
- Raytheon Company and Raytheon Missile SystemsNo. 59439, 59440, 59441June 14, 2021
- Raytheon Company and Raytheon Missile SystemsNo. 60699June 14, 2021
Same Year
- Columbia State Bank f/k/a Castle-Rose, Inc.No. 59531December 28, 2017
- Fluor Federal Solutions, LLCNo. 61431-983December 28, 2017
- Goodwill Services, Inc.No. 61439December 27, 2017
- Suffolk Construction Company, Inc.No. 60990December 27, 2017
- Parsons Government Services, Inc.No. 60218December 21, 2017
- Parsons Government Services, Inc.No. 60221December 21, 2017
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026
- U.S. Aeroteam, Inc.No. 61972, 61973August 6, 2026
- Raytheon Company and Raytheon Missile SystemsNo. 59435, 59436, 59437, 59438, 60056, 60057, 60058, 60059, 60060, 60061May 14, 2026
- IAP Worldwide Services, Inc.No. 62638, 63879May 6, 2026
- CACI International, Inc.No. 63663March 10, 2026