KBJ, Inc. appealed a contracting officer's final decision denying its claim for suspension and delay costs under a contract with NASA. The Board partially sustained the appeal, awarding KBJ $114,191.67 for unabsorbed overhead costs.

Material Facts

  • NASA awarded the contract to KBJ on 16 March 2011 for a firm-fixed-price of $3,621,900.
  • The contract required KBJ to replace two boilers at NASA's Glenn Research Center.
  • NASA issued a suspension directive on 26 May 2011, delaying the demolition of existing boilers until new ones were on site.
  • KBJ submitted a claim for $558,791.33 on 4 October 2012, which was denied by the CO on 30 November 2012.
  • The Board found that NASA's suspension directive caused a delay of 109 days.

Parties

Appellant
KBJ, Inc.
Respondent Agency
NASA
Contract Number
NNC11CA18C
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.