58992

Alion Science and Technology Corporation

November 10, 2015Judge Melnick
Denied / Government PrevailedAccord & Satisfaction / Release / WaiverStatute of Limitations / TimelinessFailure to Prosecute / DismissalDCAA InvolvedDCMA Involved

Alion Science and Technology Corporation appealed a final decision from the Defense Contract Management Agency regarding penalties for allegedly including unallowable costs in its final indirect cost rate proposal for FY 2005. The Board denied Alion's motion for summary judgment, finding that the government's claim was not time-barred.

Material Facts

  • Alion submitted its final indirect cost rate proposal for FY 2005 on 31 March 2006.
  • The government asserted a claim for penalties against Alion for including unallowable costs in its proposal.
  • The ACO determined that Alion's original submission did not include Schedule H, which was necessary for the audit.
  • DCAA issued an audit report on 19 April 2012 questioning numerous cost elements within Alion's proposal.
  • The ACO issued a final decision on 21 August 2013 asserting a claim for penalties amounting to $338,921.

Parties

Appellant
Alion Science and Technology Corporation
Respondent Agency
Defense Contract Management Agency
Contract Number
DAAB07-03-D-C213 et al.
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.