59116

Precision Standard, Inc.

July 13, 2015Judge Hartman
Denied / Government PrevailedContract InterpretationTermination for DefaultFailure to Prosecute / DismissalDCMA Involved

Precision Standard, Inc. appealed the termination of its contract for default by the government, which claimed the appellant failed to deliver a required first article on time. The Board granted the government's motion for summary judgment, affirming the termination.

Material Facts

  • The contract required Precision Standard, Inc. to submit a first article for testing by February 9, 2009.
  • PSI submitted a first article over three months late, on May 21, 2009, but it was missing required material certifications.
  • The contracting officer advised PSI that it could re-submit the disapproved first article after correcting discrepancies.
  • PSI failed to respond to the contracting officer's requests and did not submit a second first article by the specified date of January 22, 2013.
  • The contracting officer notified PSI of the potential termination for default and provided opportunities to present facts regarding the delay.
  • PSI did not respond within the specified time frame and failed to submit the first article by the final due date of October 18, 2013.

Parties

Appellant
Precision Standard, Inc.
Respondent Agency
Defense Logistics Agency
Contracting Agency
Defense Logistics Agency Aviation
Contract Number
SPM4A7-08-M-B239
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.