Chloeta Fire, LLC appealed a decision regarding its contract for a prescribed burn on federal land, asserting it completed the work and was entitled to full payment. The Board found in favor of Chloeta, concluding that the government accepted the work as complete.
Material Facts
- The government awarded Contract No. W9128F-l l-M-E023 to Chloeta on 23 September 2011.
- The contract required Chloeta to perform a prescribed burn on approximately 650 acres of federal land.
- Chloeta was paid a partial payment of $19,000 for on-site preparations.
- The contract was modified to increase the total price to $74,689.41 due to unavoidable weather delays.
- Chloeta performed a burn on 27 April 2013, consuming approximately 60-70% of Eastern Red Cedars on-site.
- Chloeta submitted an invoice for $55,689.41, but the government only paid $43,739.10.
- Chloeta submitted a claim for $11,950.31, asserting it completed the work under the contract.
- The contracting officer issued a final decision denying Chloeta's claim, stating the contractor did not burn over 100 acres as required.
Parties
- Appellant
- Chloeta Fire, LLC
- Respondent Agency
- U.S. Army Corps of Engineers
- Contract Number
- W9128F-l l-M-E023
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Sierra Nevada CorporationNo. 63649February 24, 2026
- Sierra Nevada CorporationNo. 63933, 63934February 24, 2026
- Synergetic Technologies Group, Inc.No. 64361January 29, 2026
- Repeat Consultants International, LLCNo. 64188, 64189December 8, 2025
- Novielli Boat Builders Inc.No. 64281December 5, 2025
- United Capital Investments GroupNo. 64163December 2, 2025
Same Year
- Lawn Legends LLCNo. 59078December 30, 2015
- Soluciones Especializadas de Transporte S.A.No. 58579December 29, 2015
- First Transit, Inc.No. 59700December 22, 2015
- Xerox CorporationNo. 60117December 22, 2015
- EMTA Insaat A.S.No. 60031December 18, 2015
- Soap Creek Marina, LLCNo. 59445December 18, 2015
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- Vigor Marine, LLCNo. 63405September 24, 2026
- US Military CorpNo. 64321September 24, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026