5997760000

4H Construction Corporation

April 17, 2019Judge Kinner
Sustained / Appellant PrevailedQuantum / DamagesTermination for ConvenienceDCAA Involved

4H Construction Corporation appealed the Army's refusal to pay costs incurred for a stand-by dredging contract that was terminated for convenience before a notice to proceed was issued. The Board found in favor of 4H, awarding it costs incurred in preparation for contract performance.

Material Facts

  • 4H bid on the Arkansas River dredging contract three times.
  • The Army terminated the contract for convenience prior to issuing a notice to proceed.
  • 4H incurred costs preparing to perform the contract without receiving a notice to proceed.
  • The contracting officer's email regarding a protest was deemed unclear and not a valid stop-work order.
  • DCAA audited 4H's settlement proposal and questioned certain costs, but the IQAD report later supported 4H's claims.

Parties

Appellant
4H Construction Corporation
Respondent Agency
Department of the Army
Contracting Agency
U.S. Army Engineer District, Little Rock
Contract Number
W9127S-12-D-0026
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.