Material Facts
- The contract was a firm-fixed-price contract awarded to ABC for the installation of a sniper screen in Kabul, Afghanistan.
- ABC incurred $67,793 in costs for materials and stand-by labor prior to the issuance of a notice to proceed.
- The government issued a stop-work order on 23 February 2016, and the contract was terminated for convenience effective 28 February 2016.
- ABC's termination settlement proposal requested $67,793, including $55,893 for supplies and $11,900 for labor costs.
- The CO determined that ABC was aware it was prohibited from incurring costs prior to the notice to proceed.
Parties
- Appellant
- American Boys Construction Company
- Respondent Agency
- Department of the Army
- Contract Number
- W56SGK-16-C-0013
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- KBR Services, LLCNo. 63870, 63956August 24, 2026
- AeroKool Aviation CorporationNo. 64377August 24, 2026
- Kropp Holdings, Inc.No. 64523August 24, 2026
- BFBC, LLCNo. 64509August 18, 2026
- Mvation Worldwide Inc.No. 64633August 18, 2026
- Perma-Fix Environmental Services, Inc.No. 64438July 30, 2026
Same Year
- Columbia State Bank f/k/a Castle-Rose, Inc.No. 59531December 28, 2017
- Fluor Federal Solutions, LLCNo. 61431-983December 28, 2017
- Goodwill Services, Inc.No. 61439December 27, 2017
- Suffolk Construction Company, Inc.No. 60990December 27, 2017
- Parsons Government Services, Inc.No. 60218December 21, 2017
- Parsons Government Services, Inc.No. 60221December 21, 2017
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- Vigor Marine, LLCNo. 63405September 24, 2026
- US Military CorpNo. 64321September 24, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026