DISMISSED WITH PREJUDICE: July 12, 2011
CBCA 2343
LAKESHORE ENGINEERING SERVICES, INC.,
Appellant,
v.
AGENCY FOR INTERNATIONAL DEVELOPMENT,
Respondent.
Sarah Arnold of Lakeshore Engineering Services, Inc., Detroit, MI, counsel for
Appellant.
The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.
Sarah Rapawy, Office of the General Counsel, Agency for International Development, Washington, DC, counsel for Respondent.
DANIELS, Board Judge (Chairman).
Order
The Agency for International Development terminated for the convenience of the Government a contract with Lakeshore Engineering Services, Inc. for the renovation of a dormitory and construction of a dining facility in Afghanistan. The contractor submitted a termination for convenience settlement proposal. When the agency did not act on that proposal, the contractor resubmitted it as a certified claim in the amount of $600,202. Subsequently, the contractor appealed to the Board from the agency’s deemed denial of the claim.
_________________________
2 CBCA 2343
The parties have now settled the case. The agency has paid to the contractor $494,571, inclusive of interest, and the parties have asked the Board to dismiss the case with prejudice to its reinstatement.
Accordingly, the case is DISMISSED WITH PREJUDICE.
STEPHEN M. DANIELS
Board Judge
This is a verbatim capture of the text layer of the Board's own document in Lakeshore Engineering Services, Inc., CBCA 2343. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.