CBCA 3411

Project Solutions Group

Oct 23, 2013Judge SheridanDEPARTMENT OF TRANSPORTATION
Not published in the listingDenied

Key Facts

Appellant
Project Solutions Group
Respondent agency
DEPARTMENT OF TRANSPORTATION
Judge
Sheridan
Case number
CBCA 3411
Decided
Oct 23, 2013The decision states Oct 23, 2013 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
McManus Darden & Felson LLP
Outcome
Denied
For the reasons set forth above, the appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Small claims and accelerated procedureTermination for defaultJurisdiction and timelinessChanges and equitable adjustmentDiffering site conditionsDelay, suspension and acceleration

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Joseph A. McManus, Jr. and Eric J. Darden and David J. Butzer
McManus Darden & Felson LLP
Washington, DC
For the respondent
Lynn Deavers and Bonnie Angermann and Terrence Carlson
Office of General Counsel, Department of Transportation
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision6 pages, 11,326 characters, read from the Board's own documentDecided Oct 23, 2013 on its own faceRespondent DEPARTMENT OF TRANSPORTATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 1 of them opens at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Court of Claims and Claims Court1
Perini Corp. v. United States381 F.2d 403(Ct. Cl. 1967)

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: October 23, 2013

CBCA 3411

PROJECT SOLUTIONS GROUP,

Appellant,

v.

DEPARTMENT OF TRANSPORTATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Joseph A. McManus, Jr., Eric J. Darden, and David J. Butzer of McManus Darden & Felson LLP, Washington, DC, counsel for Appellant.

Lynn Deavers, Bonnie Angermann, and Terrence Carlson, Office of General Counsel, Department of Transportation, Washington, DC, counsel for Respondent.

SHERIDAN, Board Judge.

Appellant, Project Solutions Group (PSG), elected to have this appeal processed under Board Rule 52, Small Claims Procedure, requiring a decision on the appeal within 120 calendar days from receipt of the election. 48 CFR 6101.52 (2012). Appellant meets the requirements for the small claims procedure as set forth in the Contract Disputes Act, as it is a small business concern and its claim is for $150,000 or less. 41 U.S.C. § 7106 (b) (Supp. IV 2011). Due to the shutdown of the Federal Government, from October 1 through October17, 2013, the Board was unable to issue this decision within 120 calendar days from the date of election. The decision in this appeal is final and conclusive and cannot be set aside except in case of fraud. 48 CFR 6101.52(b). The decision has no value as precedent. Id.

On September 25, 2009, Department of Transportation (DOT) entered into contract GS-29F-0022T with PSG to provide planning, design management, construction management, and coordination services associated with renovations of the cafeteria and kitchen at DOT’s headquarters building in Washington, D.C. As part of contract performance, PSG was to replace the kitchen flooring to fix drainage problems. PSG suggested the use of PROTECT-ALL flooring in the kitchen, and DOT approved its use. On November 7, 2010, PSG’s subcontractor began demolition of the area and removed the pre-existing quarry tile flooring. Dennis Davidson, who was DOT’s project manager on the job site, remembers that during the demolition of the floor, PSG’s subcontractor hosed water over the floor for three consecutive days, in an attempt to keep the dust down in the area. Nearby areas remained occupied by DOT staff, so it was important that the demolition dust be controlled. David Zorger, partner and co-founder of PSG, noticed that the concrete slab under the quarry tile was extremely wet. Soon after demolition was complete, on November 25 and 26, PSG’s subcontractor poured Combimix over the concrete floor slab. Combimix is a cement-based sub-flooring and leveling material. On November 29, water was poured on the floor to check the slope of drainage. Also around November 29, PSG’s subcontractor noted that the Combimix underlayment was “still too moist” to install the PROTECT-ALL flooring.

Prior to installing the PROTECT-ALL flooring, PSG was required to test the relative humidity (RH) levels of the concrete floor slab that was under the Combimix installation. RH tests taken at four locations on November 29, 2011, showed RH readings of 96%, 95%, 100%, and 93%. Tests taken on December 2, 2011, showed the RH readings had lowered slightly to 95%, 95%, 99%, and 92%. On December 6, the RH readings were 94%, 94%, 99%, and 91%.

On December 8, 2011, PSG wrote George Fields, the senior project executive for DOT’s headquarters building, to inform DOT that PSG had concerns regarding the RH level in the concrete floor slab in the kitchen. PSG informed Mr. Fields that, as of December 8, 2011, the RH levels of the concrete slab “have exceeded the acceptable RH range,” and that the PROTECT-ALL flooring “requires a constant RH level of 70% to 75%” to be properly installed. PSG went on to reference “continued delay to PSG work and the costs being incurred by PSG and its contractors as a result of the delay.” PSG stated that it and its contractors and consulting engineers “have investigated the sources that may be contributing to the higher than normal or expected RH levels . . . [and] we believe the issue may be related to the lack of control of the relative humidity below the first floor concrete substrate within the area of work.” PSG stated:

The unstable and high RH levels continue to prevent PSG from moving forward with the installation of the new flooring product along with the remaining project tasks required to complete this project.

. . . .

As of this date, the project is approximately two weeks delayed due to the ongoing high RH levels. Without specific direction from DOT as to how to address and resolve this mater, the delays in completing this project continue.

Be advised that the issue of direction is critical as the present delay is severely impacting our cost.

RH tests were taken at four locations on December 9, 2011, that showed RH readings of 73%, 83%, 81%, and 84%. Tests taken on December 14 showed the RH readings had lowered to 59%, 67%, 64%, and 71%. After the December 14th readings, subsequent RH readings taken in the following week showed that the RH levels remained below 75%, and in the range of 69% to 47%.

On December 15, 2011, Mr. Fields responded to PSG’s December 8 letter, noting that PSG had requested “specific direction” as to how DOT wanted to resolve the RH matter to move the project forward. Mr. Fields directed: Based on the most recent RH readings in the construction area, we hereby authorize PSG to immediately move forward with the installation of the PROTECT-ALL flooring in the kitchen area. These readings were taken using the RH Rapid situ probes having an accuracy of +/- 2% from 50% to 90% range. The testing results for December 14, 2011, are listed below for your review. These readings are below the [PROTECT-ALL flooring manufacturer’s] requirements listed inside the September 2011 installation manual 3b-ii-2 of 75% to 80% relative humidity.

Test Results:

Probe # RH

1 59%

2 67%

3 64%

4 71%

PSG did not resume work on the project. On January 19, 2012, DOT contracting officer Cynthia Vass-Lassiter issued a cure notice giving PSG ten days to correct, among other things, its failure to install the PROTECT-ALL flooring, or face possible termination. PSG asked to meet with the contracting officer but a meeting was not able to be convened until January 26; Ms. Vass-Lassiter extended the deadline for PSG’s response to the cure notice to January 31, 2012.

At the January 26 meeting, DOT agreed to pay a $99,110.57 progress payment which had been previously invoiced but rejected. According to Mr. Zorger, when he left the January 26 meeting, he believed that DOT had acquiesced to his position that PSG would not resume working on the project until it received the $99,110.57 payment. DOT disputes Mr. Zorger’s impression and posits that after Mr. Fields’ December 15 directive, DOT never told PSG it could continue to not work. DOT emphasizes that its employees were greatly inconvenienced by a non-working kitchen and it incurred extra costs to its food services contractor while the kitchen was not able to be used. Completion of the kitchen renovation was a priority for DOT.

Notwithstanding the agreement made on January 26 that DOT would pay PSG the $99,110.57 invoice, because of what appears to be confusion and/or lack of attention on the part of DOT, payment was not made until mid-March 2012. PSG did not resume work on the project until after it received the payment; the project was completed approximately three weeks later.

On January 31, 2012, PSG provided the contracting officer a breakout of the costs it was seeking to complete the kitchen ($34,394.17), delay costs ($19,983.39), and a completion schedule showing it would be resuming work on the site on February 2, 2012. A request for an equitable adjustment seeking $116,063.23 followed on April 20, 2012. On March 19, 2013, PSG submitted a certified claim to the contracting officer seeking $136,628.77, “based on the hidden condition of unusually high moisture encountered in the existing concrete slab under the kitchen flooring.” When the contracting officer failed to issue a final decision, PSG appealed the deemed denial of its claim, which was docketed as CBCA 3411.

Discussion

This Board in Quality Forests, Inc. v. Department of Agriculture, CBCA 123, 07-1 BCA ¶ 33,490, made clear that, with regard to latent differing site conditions: The contractor bears the burden of establishing by a preponderance of the evidence that “the unknown physical condition must be one that could not be reasonably anticipated by the contractor from his study of the contract documents, his inspection of the site, and his general experience[,] if any, as a contractor in the area.” Randa/Madison Joint Venture III v. Dahlberg, 239 F.3d 1264, 1276 (Fed. Cir. 2001) (quoting Perini Corp. v. United States, 381 F.2d 403, 410 (Ct. Cl. 1967)).

DOT had concluded that PSG had not completed the percentage of work PSG asserted was complete.

Thus, PSG bears the burden of establishing that it encountered a unknown physical condition when it discovered high RH levels in the kitchen slab. Considering the facts presented by this case, we do not believe that the high RH levels in the kitchen should have been unknown to a knowledgeable contractor, which PSG purports to be.

To keep the dust down, PSG used significant amounts of water hosing the concrete slab over several days of demolition; it then poured an underlayment material on top of that. PSG’s first testing of RH levels showed levels of 96%, 95%, 100%, and 93%. Other than asking DOT to increase heat levels in the building, it does not appear that PSG or its subcontractors used any means, such as large fans or electric heaters, to dry the area. A reasonable contractor, planning to saturated the concrete floor slab with water to keep down dust, should have included processes and time in its schedule to dry out the area. PSG failed to include either in its planning.

Reviewing the December RH testing data, it appears that beginning December 9, the RH levels began to decrease dramatically and steadily. As of December 14, the RH levels of the concrete slab were below the levels needed for installation of the PROTECT-ALL flooring. Yet PSG did not return to the job site and begin the installation.

While PSG offered a few theories on what caused high RH levels in the concrete slab, none of those theories was compelling. We conclude that the early high RH levels in the concrete slab were caused by appellant’s own actions, when it saturated the slab with water for three days during demolition and then failed to allow time for the slab to dry out before covering it. Appellant further delayed the project by failing to resume work once the slab was sufficiently dry. Appellant has not established any government-caused delay associated with the high RH levels in concrete slab. The fact that at some point the contracting officer offered to pay PSG for five days of delay has no bearing on our decision because the Board considers claims de novo.

Any delay associated with the high RH levels in the concrete slab that may have occurred was caused by PSG and/or its subcontractors when the area was hosed down to control demolition dust. Even though it was able to install the PROTECT-ALL flooring, and directed by DOT to do so, PSG refused to return to the project until it had actually received the $99,110.57 progress payment.

Decision

For the reasons set forth above, the appeal is DENIED.

PATRICIA J. SHERIDAN

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Project Solutions Group, CBCA 3411. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.