CBCA 3498

Crockett Facilities Services, Inc.

Dec 13, 2013Judge GoodmanGENERAL SERVICES ADMINISTRATION
Not published in the listingGranted

Key Facts

Appellant
Crockett Facilities Services, Inc.
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Goodman
Case number
CBCA 3498
Decided
Dec 13, 2013The decision states Dec 13, 2013 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
Brown Gains, LLC
Outcome
Granted
As respondent has conceded the appeal on the merits, the appeal is GRANTED in the amount of $26,6440.80, payment of $2,664.48 for each month after August 2013 until satisfaction of the claim, and applicable interest pursuant to the Contract Disputes Act.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

EAJA and feesPayment and interestSmall claims and accelerated procedure

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Eden Brown Gaines
Brown Gains, LLC
White Plains, MD
For the respondent
Claire L. O’Donnell
Office of General Counsel, General Services Administration
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision3 pages, 3,553 characters, read from the Board's own documentDecided Dec 13, 2013 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Federal Acquisition Regulation1
Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

GRANTED: December 13, 2013

CBCA 3498

CROCKETT FACILITIES SERVICES, INC.,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Eden Brown Gaines of Brown Gains, LLC, White Plains, MD, counsel for Appellant.

Claire L. O’Donnell, Office of General Counsel, General Services Administration, Washington, DC, counsel for Respondent.

Before GOODMAN, Board Judge.

On August 16, 2013, Crockett Facilities Services, Inc. (CFSI or appellant) filed a notice of appeal from a deemed denial by a General Services Administration (GSA or respondent) contracting officer of appellant’s claim pursuant to the Contract Disputes Act. Appellant’s claim was submitted to the contracting officer on May 14, 2013. Pursuant to Board Rule 52, 48 CFR 6101.52 (2012), appellant elected the small claims procedure. Accordingly, this decision is final and conclusive and has no value as precedent. In its notice of appeal, designated as its complaint, appellant stated: Nature of Claim: Pursuant to Modification P003 of the above referenced Contract, and executed August 16, 2011, CFSI agreed to provide additional inventory. . . .The Modification facilitated payment for additional inventory at the amount of $2,664.48 per month for Option Year III. . . .

When GSA formally exercised Option Year III by Modification P006, the contracting office inadvertently omitted the line item for the additional inventory. . . . CFSI contacted the contracting office to confirm the existence of requirements for additional inventory and payment for the same. The contracting office confirmed that an adjustment to the contract, to include the additional inventory, was forthcoming. . . .

Despite the communication from the contracting office confirming the government’s intent that CFSI provide service to the additional inventory and despite CFSI’s continued provision of such services, the Contracting Officer has not made appropriate adjustments to the Contract to facilitate payment to CFSI.

CFSI is entitled to payment of $26,644.80, plus interest pursuant to the Prompt Payment Act and/or FAR 52.233-1(h), as representative of payments owed for the period between November 1, 2012 and August 31, 2013. CFSI is entitled to $2,664.48 each month thereafter, plus interest pursuant to the Prompt Payment Act and/or FAR 52.233-1(h), until the satisfaction of its claim.

Relief Requested: CFSI seeks payment in the amount of $26,644.80, plus accrued interest; payment of $2,664.48 for each month until satisfaction of the claim; an appropriate modification to the Contract reflecting payment in the amount of $2,664.48 per month to service the additional inventory; and attorney fees and costs.

Respondent requested extensions of time to file an answer and an appeal file, and these requests were granted by the Board. Appellant and respondent entered into settlement discussions but did not resolve the dispute by agreement. On December 9, 2013, respondent filed a stipulation that stated: “Respondent, General Services Administration, concedes the . . . appeal on the merits.”

Decision

As respondent has conceded the appeal on the merits, the appeal is GRANTED in the amount of $26,6440.80, payment of $2,664.48 for each month after August 2013 until satisfaction of the claim, and applicable interest pursuant to the Contract Disputes Act. The Board cannot address appellant’s demand for attorney fees and costs in this proceeding. __________________________

ALLAN H. GOODMAN

Board Judge

If appellant believes it is entitled to attorney fees and costs, it may proceed pursuant to Board Rule 30.

This is a verbatim capture of the text layer of the Board's own document in Crockett Facilities Services, Inc., CBCA 3498. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.