CBCA 6198

Eagle Peak Rock & Paving, Inc.

Oct 23, 2018Judge RussellDEPARTMENT OF TRANSPORTATION
OrderRuled on a motion

Key Facts

Appellant
Eagle Peak Rock & Paving, Inc.
Respondent agency
DEPARTMENT OF TRANSPORTATION
Judge
Russell
Case number
CBCA 6198
Decided
Oct 23, 2018The decision states Oct 23, 2018 on its own face, which agrees with the listing.
Decision type
Order
Law firm for the appellant
Varela, Lee, Metz & Guarino, LLP
Outcome
Ruled on a motion
For the foregoing reasons, we deny FHWA's motion to dismiss this appeal.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Termination for defaultTermination for convenienceCosts and quantum

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Bennett J. Lee and Stephen L. Pessagno
Varela, Lee, Metz & Guarino, LLP
San Francisco, CA
For the appellant
David B. Wonderlick
Varela, Lee, Metz & Guarino, LLP
Tysons Corner, VA
For the respondent
Rayann L. Speakman and Western Federal Lands Highway
Division, Federal Highway Administration, Department of Transportation
Vancouver, WA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision3 pages, 5,201 characters, read from the Board's own documentDecided Oct 23, 2018 on its own faceRespondent DEPARTMENT OF TRANSPORTATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

ORDER DENYING RESPONDENT’S MOTION TO DISMISS:

October 23, 2018

CBCA 6198

EAGLE PEAK ROCK & PAVING, INC.,

Appellant,

v.

DEPARTMENT OF TRANSPORTATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Bennett J. Lee, and Stephen L. Pessagno of Varela, Lee, Metz & Guarino, LLP, San Francisco, CA; and David B. Wonderlick of Varela, Lee, Metz & Guarino, LLP, Tysons Corner, VA, counsel for Appellant.

Rayann L. Speakman, Western Federal Lands Highway Division, Federal Highway Administration, Department of Transportation, Vancouver, WA, counsel for Respondent.

Before Board Judges KULLBERG, SULLIVAN, and RUSSELL.

RUSSELL, Board Judge.

Appellant, Eagle Peak Rock and Paving, Inc. (Eagle Peak), filed this appeal of the Federal Highway Administration’s (FHWA or agency) deemed denial of Eagle Peak’s claim for termination for convenience costs. FHWA has moved to dismiss this appeal because the Board has not yet adjudicated the merits of the underlying termination for default. For the reasons set forth below, we deny FHWA’s motion.

Background

Prior to the filing of this appeal, Eagle Peak filed two other cases with the Board – CBCA 5692, in which it challenges the FHWA’s termination for default of the parties’ 2 CBCA 6198

contract for construction work in Yellowstone National Park, and CBCA 5955, in which it seeks damages for alleged improper retainage of payments.

In support of its motion to dismiss this appeal, FHWA notes that Eagle Peak’s appeal of the agency’s termination for default (CBCA 5692) is pending and the relief requested therein has not been granted (specifically, converting the default termination to one for convenience). Thus, the agency asserts that any review of the merits of this appeal based on quantum for a termination for convenience is premature and, for this reason, the appeal should be dismissed.

Eagle Peak opposes the motion arguing that the Board acquired jurisdiction at the time of the contracting officer’s deemed denial of Eagle Peak’s claim. The company adds that, in filing its appeal, it is exercising “its right to pursue the most expeditious reversal” of the consequences of the termination. Eagle Peak requests that the Board deny FHWA’s motion or, in the alternative, stay this appeal pending the conclusion of CBCA Nos. 5692 and 5955.

Discussion

FHWA does not argue that, pursuant to Board Rule 8(b), 48 CFR 6101.8(b), the Board lacks jurisdiction over the appeal nor does it argue that, pursuant to Board Rule 8(e), Eagle Peak’s complaint fails to state a claim upon which relief may be granted. Instead, FHWA asserts that dismissal is warranted for the purpose of litigative efficiency, i.e., Eagle Peak’s termination for default should be decided prior to the start of litigation on quantum. The agency’s position is not without support. See, e.g., Aerosonic Corporation, ASBCA 42696, 91-3 BCA ¶ 24,212, at 121,117-18.

However, the practice of dismissing as premature convenience claims prior to resolution of related default claims is not universal among tribunals. Indeed, a predecessor Board has taken a contrary position–specifically, allowing a challenge to a default termination (i.e., the entitlement claim) and a claim for termination for convenience settlement costs (i.e., the quantum claim) to proceed concurrently. Fischer Imaging Corporation, VABCA No. 6343, et al., 02-2 BCA ¶ 32,048, at 158,384; Delfour, Inc., VABCA No. 3900, et al., 94-1 BCA ¶ 26,385, at 131,269. And one court has analogized the default/convenience termination claims to a traditional breach of contract/damages claim – concluding that “the [termination for convenience costs remedy] is a substitute for the damages component of a breach of contract action.” Boeing Company v. United States, 31 Fed. Cl. 289, 296 (1994). Thus, a party may challenge the merits of a default termination and, at the same time, “plead that damages are presently due and owing” because of the termination. Id.

3 CBCA 6198

In this appeal, Eagle Peak is seeking relief for monetary damages due and owing (i.e., termination for convenience costs) in the event that its separate appeal challenging the termination for default is decided in its favor. We are inclined to agree with those tribunals holding that litigative efficiency is not a sufficient basis to dismiss this appeal. Neither the Board’s Rules nor the Federal Rules of Civil Procedure contemplates dismissal on this basis. See Board Rule 8; Fed. R. Civ. P. 12(b). Further, any concern regarding potential litigative inefficiency in proceeding concurrently with entitlement and quantum claims can be readily addressed through case management of the two appeals.

Decision

For the foregoing reasons, we deny FHWA’s motion to dismiss this appeal. FHWA must answer the complaint and file any documents pursuant to Board Rule 4 by no later than Friday, November 23, 2018.

Beverly M. Russell

Board Judge

We concur:

H. Chuck Kullberg

Board Judge

Marian E. Sullivan

Board Judge

In its Motion to Extend Deadline filed on August 22, 2018 which was granted, FHWA noted that if the Board denies the Government’s Motion to Dismiss, “the Government will be able to put together a Rule 4 Appeal File relatively quickly due to the limited documents.”

This is a verbatim capture of the text layer of the Board's own document in Eagle Peak Rock & Paving, Inc., CBCA 6198. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.