56236

Senate Builders & Construction Managers, Inc.

July 23, 2010Judge Dickinson
OtherContract InterpretationAccord & Satisfaction / Release / Waiver

Senate Builders & Construction Managers, Inc. appealed for compensation for additional work and remission of liquidated damages under a task order contract with the Army. The Board granted the government's motion for partial summary judgment on certain claims while denying others.

Material Facts

  • Senate Builders & Construction Managers, Inc. was issued a task order by the United States Army to repair aircraft pavements.
  • The task order was for a lump sum price of $528,080 and required completion within 120 days.
  • Senate sought compensation for additional work and remission of liquidated damages assessed by the government.
  • The contract included clauses related to disputes, differing site conditions, and changes.
  • Senate's subcontractor recognized the possibility of repairs deeper than two inches and included contingency pricing in its bid.
  • The government assessed liquidated damages of $30,400.00 for delays in completion.

Parties

Appellant
Senate Builders & Construction Managers, Inc.
Respondent Agency
United States Army
Contracting Agency
Pennsylvania Air National Guard
Contract Number
W912KC-05-C-0003
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.