Solid State Electronics Corporation
Solid State Electronics Corporation appealed a contracting officer's decision partially denying its claim for expedited shipping costs under Contract No. SPM7MO-08-M-1365. The Board granted the government's motion for summary judgment, allowing only a portion of the claimed costs.
Material Facts
- The Defense Supply Center, Columbus issued a unilateral purchase order to the appellant for an electromagnetic relay.
- The purchase order required delivery by the fastest traceable means possible and allowed early shipment at no additional charge to the government.
- The contracting officer allowed $168.14 for overnight shipping costs but disallowed the remaining $487.75 claimed by the appellant.
- The appellant invoiced the government for $5,520.99, which included shipping costs.
- The appellant submitted a claim for $655.89 for shipping costs and additional costs incurred in expediting the shipping.
Parties
- Appellant
- Solid State Electronics Corporation
- Respondent Agency
- Defense Supply Center, Columbus
- Contract Number
- SPM7MO-08-M-1365
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Matrix Research, Inc.No. 56430, 56431June 22, 2011
- J.E. McAmis, Inc.No. 54455, 54456, 54457November 19, 2010
Same Year
- C.E.M.E.S. S.p.A.No. 56253, 57355December 29, 2010
- Shaw Environmental, Inc.No. 57237December 16, 2010
- Thorington Electrical and Construction CompanyNo. 56997December 13, 2010
- Phoenix Management, Inc.No. 57234December 13, 2010
- Parsons Global Services, Inc.No. 56731December 3, 2010
- Kelly-Ryan, Inc.No. 57168November 29, 2010
Same Issue
- Africa Transport Logistics CompanyNo. 64120October 1, 2026
- Huffman Construction, LLCNo. 62591, 62783September 30, 2026
- Martin Brothers ConstructionNo. 63196, 63431September 30, 2026
- Vigor Marine, LLCNo. 63405September 24, 2026
- US Military CorpNo. 64321September 24, 2026
- Scot Cardillo dba Engineers Tooling SupportNo. 61612September 22, 2026