58633

Engineering Solutions & Products, LLC

May 13, 2015Judge Paul
Denied / Government PrevailedAccord & Satisfaction / Release / WaiverContract Interpretation

Engineering Solutions & Products, LLC appealed a contracting officer's decision denying its claim for costs associated with a lease agreement. The Board denied the government's motions to dismiss and for summary judgment.

Material Facts

  • ESP provides engineering, technical, and consulting services primarily to the Department of Defense (DoD).
  • In April 2003, ESP responded to a solicitation issued on behalf of the Army's Project Manager Soldier Equipment activity.
  • ESP's proposal included the lease of renovated storage space at a location in Haymarket, Virginia.
  • The Army transferred funds in excess of $2 million to FedSource-Beaufort for the lease and maintenance of the storage facility.
  • ESP renegotiated its lease to increase the total amount of leased space at the Haymarket facility to 236,082 square feet.
  • The Army rejected ESP's invoices for reimbursement of early termination costs.
  • ESP filed a certified claim for the amounts at issue on 6 December 2012, which was denied in its entirety by the CO on 5 April 2013.

Parties

Appellant
Engineering Solutions & Products, LLC
Respondent Agency
Department of the Army
Contracting Agency
Department of the Treasury
Contract Number
000000-00-0-0000
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.