58634

Parsons Evergreene, LLC

September 5, 2018Judge Clarke
Partially SustainedCost Allowability / Allocability (FAR 31)Quantum / DamagesContract Changes / Constructive ChangesContract InterpretationDiffering Site ConditionsDelay / Disruption / SuspensionAccelerationDefective SpecificationsInspection / Acceptance / Warranty / Latent DefectsLiquidated DamagesPayment / Progress Payments / FinancingStatutory ComplianceDCAA Involved

Parsons Evergreene, LLC appealed a contracting officer’s denial of claims arising from the design and construction of temporary lodging and visitor-quarters facilities at McGuire Air Force Base. The Board sustained the appeal in part and denied it in part, sustaining the appeal in the amount of $10,519,082.

Material Facts

  • The project used a Design-Build-Plus 03 process with a 35% concept design followed by design completion and construction.
  • Delivery Order No. 0013 provided fixed prices for design and construction of the Temporary Lodging Facility and Visiting Quarters and required completion by 5 March 2007.
  • The 35% Visiting Quarters design did not adequately account for progressive collapse, although progressive-collapse resistance was required.
  • Pre-bid answers stated that the drawings were concept only and that bidders could substitute assemblies and structural systems to comply with progressive-collapse requirements.
  • The government directed Parsons to proceed with the Baker 35% double-wall design after rejecting Parsons’s structural-brick alternative.
  • The project encountered unsuitable fill, an organic layer, and a transite asbestos-insulated pipe in the Visiting Quarters foundation area.
  • The government-provided utility information did not identify several utilities encountered during installation of the high-temperature hot-water line.
  • The government continued to require elimination of oil canning in the standing-seam metal roof despite an amendment stating that oil canning was inherent in the product and should be seriously minimized.
  • The government approved and later rescinded Architect’s Supplemental Instruction No. 13 concerning Sherwin Williams paint in the Visiting Quarters.
  • The government conducted multiple closeout inspections over approximately four months before beneficial occupancy on 11 September 2008.
  • DCAA audited Parsons’s claim and found that the claimed costs were incurred, but questioned most costs based on the Air Force’s technical evaluation.
  • The contracting officer’s final decision dated 27 March 2013 denied or partially allowed the claim components, and Parsons appealed.

Parties

Appellant
Parsons Evergreene, LLC
Respondent Agency
Air Force
Contracting Agency
Air Force
Contract Number
FA8903-04-D-8703
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.