Amaratek appealed for compensation related to work performed during a government shutdown under Contract No. W9124R-11-P-1054. The Board partially sustained the appeal, awarding a specific amount for services rendered.

Material Facts

  • The Department of the Army awarded Amaratek Contract No. W9124R-11-P-1054 for material analysis laboratory services.
  • The total award amount was $977,432, with a base period and two option periods.
  • The government ordered Amaratek to stop work on 1 October 2013 due to a government shutdown.
  • Amaratek submitted an invoice for $62,718.35 for services in October 2013, which was rejected by the government.
  • Amaratek filed a REA for $69,677, which included $58,947 for services and $10,730 for additional costs due to the shutdown.
  • The REA was denied by the contracting officer on 6 February 2014, and Amaratek subsequently filed an appeal.

Parties

Appellant
Amaratek
Respondent Agency
Department of the Army
Contracting Agency
Mission & Installation Contracting Command Center-Yuma
Contract Number
W9124R-11-P-1054
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.