Relyant Global LLC
The Board partially resolved the government's motion to dismiss portions of Relyant Global LLC's complaint in consolidated appeals challenging a contract termination for default. The Board dismissed certain unsubmitted delay and design-related claims, declined to dismiss other allegations, took no further action concerning one related appeal pending another decision, and denied the request to strike complaint paragraphs.
Material Facts
- The parties' contract concerned construction services at an air base in Romania.
- The consolidated appeals challenge only the termination of the contract for default.
- Relyant alleged that flaws in the rail design caused delays and increased costs.
- Relyant also alleged that other design flaws delayed the project.
- Relyant alleged delays related to lightweight fill and #57 stone.
- The Board previously dismissed the corresponding ASBCA No. 64231 delay claim because Relyant failed to state a sum certain.
- The government identified no submittals other than those for lightweight fill and #57 stone that Relyant was pursuing in ASBCA No. 64111.
- The government requested that the Board strike paragraphs from the complaint.
Parties
- Appellant
- Relyant Global LLC
- Respondent Agency
- U.S. Army Engineer District, Europe
- Contracting Agency
- U.S. Army Engineer District, Europe
- Contract Number
- W912GB-21-D-0020
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Relyant Global LLCNo. 64199August 4, 2026
- Weil Construction, Inc.No. 62742, 63155, 64045July 29, 2026
- Relyant Global LLCNo. 64230, 64032, 64111, 64231, 64517July 29, 2026
- Wild Hare Haulers, LLCNo. 64442, 64443July 16, 2026
- Wild Hare Haulers, LLCNo. 64442, 64443June 23, 2026
- KPH Construction Corp.No. 64115, 64116May 27, 2026
Same Year
- WSP USA Solutions Inc.No. 62674September 1, 2026
- KiewitPhelpsNo. 61184, 62119, 62980, 64137September 1, 2026
- HECO Pacific Manufacturing, Inc.No. 63217, 64512September 1, 2026
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- ProLog, Inc.No. 64319August 28, 2026
- Dubai Pearl CompanyNo. 64444August 26, 2026
Same Issue
- Visionary Construction, Inc. dba Visionary ServicesNo. 64426August 20, 2026
- Peritia LLCNo. 64495, 64586August 20, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026
- Vision Distributors LLCNo. 64357July 17, 2026
- Wild Hare Haulers, LLCNo. 64442, 64443July 16, 2026
- Jaxon Construction, Inc.No. 64432June 24, 2026