Environmental Chemical Corporation

July 15, 2022Judge Thrasher
Partially SustainedContract Changes / Constructive ChangesDelay / Disruption / SuspensionDCAA InvolvedDCMA Involved

Environmental Chemical Corporation appealed two claims regarding the installation and subsequent removal of internal wiring for a contract in Afghanistan, which were denied by the Air Force Contract Officers. The Board sustained both appeals, awarding damages for the removal and replacement of wiring and for compensable delays.

Material Facts

  • The U.S. Air Force awarded Contract No. FA8903-06-D-8511 to ECC on April 12, 2006.
  • Task Order No. 0056 was awarded to ECC for the design and construction of two Headquarters Buildings in Afghanistan.
  • ECC used Vatan electrical wire, which was not on the pre-approved list but was previously accepted by the COR.
  • The government assessed liquidated damages of $429,906 due to delays in project completion.
  • ECC filed a Request for Equitable Adjustment (REA) for $1,138,669, which was denied by the government.

Parties

Appellant
Environmental Chemical Corporation
Respondent Agency
Department of the Air Force
Contract Number
FA8903-06-D-8511
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.