5940459962600506027760851

RBC Construction Corp.

July 9, 2020Judge D'Alessandris
Partially SustainedDelay / Disruption / SuspensionContract Changes / Constructive ChangesQuantum / DamagesDefective Specifications

RBC Construction Corp. appealed several final decisions from the U.S. Army Corps of Engineers regarding delays and additional costs associated with a construction contract for an Army Reserve base in Puerto Rico. The Board partially sustained the appeals, awarding some compensable delays and addressing various claims.

Material Facts

  • RBC was awarded a design/build contract for the construction of four structures at an Army Reserve base in Puerto Rico.
  • The contract was for a total of $12,356,390 and required completion within 630 calendar days.
  • RBC filed five separate certified claims related to alleged contractual changes and government-caused delays.
  • The government delayed RBC's site and foundation work due to its insistence on including hydraulic calculations for a fire cistern in the fast-track design submission.
  • RBC discovered asbestos on the project site, which required a stop-work order and additional remediation efforts.

Parties

Appellant
RBC Construction Corp.
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
W912QR-11-C-0046
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.