60648

Areyana Group of Construction Company

May 11, 2018Judge Paul
DismissedCDA Jurisdiction

Areyana Group of Construction Company appealed a contracting officer's decision denying a time extension and the return of liquidated damages. The Board dismissed the appeal due to lack of jurisdiction over the claim.

Material Facts

  • The government entered into a fixed-price contract with AGCC in a total amount of $13,058,609.03.
  • AGCC was required to design and construct the Open Bay Barracks for the Afghan National Civil Orders Police.
  • The contract included FAR clauses requiring certification for claims exceeding $100,000.
  • AGCC's request for a 188-day time extension was denied by the CO due to lack of compliance with contract requirements.
  • AGCC filed a claim on 3 October 2015 that replicated its previous REA but lacked certification.
  • The CO issued a final decision denying AGCC's claim on 17 March 2016.

Parties

Appellant
Areyana Group of Construction Company
Respondent Agency
U.S. Army Engineer District, Memphis
Contract Number
W5J9LE-12-C-0013
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.