Partially SustainedContract InterpretationContract Changes / Constructive ChangesEquitable Adjustment (REA)Government-Furnished PropertySuperior KnowledgeInspection / Acceptance / Warranty / Latent DefectsCPARS / Past-Performance EvaluationQuantum / DamagesAuthority of Government AgentsSmall Business

Fluor Federal Solutions, LLC appealed the denial of claims arising from a fixed-price regional base operations support contract, including claims concerning a missing Maximo database, asset inventories and condition, extra-contractual work, and CPARS evaluations. The Board sustained entitlement on the Maximo constructive-change claim in part, denied the remaining maintenance and asset-condition claims, and returned the CPARS issue to the Navy for reconsideration.

Material Facts

  • The Navy awarded Fluor a principally fixed-price regional base operations support contract covering four Naval installations near Jacksonville, Florida.
  • The contract required Fluor to maintain records stored in the Government’s CMMS and made the systems available for Fluor’s use.
  • The contract defined maintain as keeping something in a state of repair and efficiency and preserving it from failure or decline.
  • The contract and incorporated proposal did not include time, resources, or costs for Fluor to build a Maximo database from scratch.
  • The Navy’s Maximo data was incomplete, inaccurate, inconsistent with other source data, and not usable by Fluor for contract performance.
  • The Navy attempted to scrub and reconcile the data but suspended those efforts, leaving Fluor to recreate the database using the contract’s Section J tables.
  • The contract and solicitation repeatedly stated that equipment and systems would be provided in as-is condition.
  • The Section J inventories identified systems and major components and repeatedly informed offerors that they were not complete inventories of every component.
  • Fluor’s extra-contractual-work analysis relied on subjective coding of work orders without determining whether the work was outside the contract or had been compensated under IDIQ arrangements.
  • The Navy’s CPARS ratings relied in part on Fluor’s alleged failure to maintain the CMMS current and accurate and on related performance deficiencies.
  • The Board lacked measurable criteria and sufficient Navy evidence to determine whether the challenged CPARS ratings remained justified after the Maximo ruling.

Parties

Appellant
Fluor Federal Solutions, LLC
Respondent Agency
Department of the Navy
Contracting Agency
Naval Facilities Command Southeast (NAVFAC-SE)
Contract Number
N69450-12-D-7582
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.