61859

Raytheon Company

June 8, 2020Judge Melnick
Partially SustainedInspection / Acceptance / Warranty / Latent DefectsDelay / Disruption / SuspensionAccord & Satisfaction / Release / WaiverContract InterpretationQuantum / Damages

Raytheon Company sought summary judgment in an Army breach-of-contract claim concerning the quality and delivery timing of thermal sights. The Board granted summary judgment on the quality claim and the alleged lateness of 15 expedited sights, but denied it concerning the alleged late delivery of 132 sights under the original schedule.

Material Facts

  • The Army awarded Raytheon a contract for Improved Thermal Sight Systems to be furnished for light armored vehicles.
  • The contract included FAR 52.246-2, INSPECTION OF SUPPLIES—FIXED PRICE, and a Product Quality Deficiency Report clause instead of the proposed warranty.
  • The original schedule required delivery of 300 sights between February 28, 2012 and April 30, 2013.
  • The parties modified the contract to establish expedited delivery of 146 sights, including 15 due by August 31, 2012.
  • Raytheon delivered the 15 expedited sights between July 20 and 30, 2012.
  • The contracting officer acknowledged delivery of the 15 expedited sights and Raytheon's entitlement to the incentive fee.
  • The government inspected and accepted the last sights required by the contract on July 10, 2013.
  • After acceptance, Raytheon performed Product Quality Deficiency Report analyses for the government.
  • Raytheon repeatedly offered software updates or spare parts as consideration for schedule extensions.
  • General Dynamics issued 73 Product Quality Deficiency Reports to the government between February 25, 2012 and October 13, 2015.
  • The contracting officer who issued the final decision had been assigned to the matter only since February 2018 and did not represent that she had first-hand knowledge of when the sights were delivered.
  • The government did not identify evidence showing that it communicated a revocation of acceptance to Raytheon.

Parties

Appellant
Raytheon Company
Respondent Agency
United States Army
Contracting Agency
Army
Contract Number
W56HZV-11-C-0130
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.