61941

Fortis Networks, Inc.

June 2, 2021Judge Osterhout
Partially SustainedLiquidated Damages

Fortis Networks, Inc. appealed the assessment of liquidated damages by the U.S. Army Corps of Engineers for delays in completing a task order. The Board granted the government's motion for summary judgment in part, addressing the apportionment of liquidated damages.

Material Facts

  • The contracting officer awarded Contract No. W912BV-D-0005 on July 10, 2014.
  • The contract included a liquidated damages clause with an amount set at $988 per calendar day.
  • The government issued a solicitation for a task order on August 28, 2014, with an updated liquidated damages amount of $735 per calendar day.
  • Task Order No. 0002 was awarded on September 29, 2014, with various line items for construction work.
  • The period of performance ended on June 11, 2016, but performance was not completed until August 7, 2018.
  • The contracting officer assessed liquidated damages for 787 calendar days of delay, totaling $578,445.
  • Fortis did not file an excusable delay claim or request any extensions of time.

Parties

Appellant
Fortis Networks, Inc.
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
W912BV-14-D-0005
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.