61960

Goodloe Marine, Inc.

July 12, 2023Judge Prouty
Partially SustainedQuantum / Damages

Goodloe Marine, Inc. appealed a denial of its claim for additional costs incurred due to a government-ordered suspension of work. The Board denied the government's motion for summary judgment, allowing Goodloe's appeal to proceed.

Material Facts

  • The contract involved was a Multiple Award Task Order Contract for dredging near Tampa, Florida.
  • The contract included the FAR 52.242-14, Suspension of Work clause and a liquidated damages clause.
  • The Corps suspended work on June 15, 2012, due to Goodloe's alleged failure to prevent impacts to migratory birds.
  • The suspension lasted until September 4, 2012.
  • Goodloe submitted its claim for $1,879,000 on June 14, 2018, seeking compensation for costs incurred during the suspension.

Parties

Appellant
Goodloe Marine, Inc.
Respondent Agency
United States Army Corps of Engineers
Contract Number
W912EP-11-D-0020
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.