Sauer Incorporated
Sauer Incorporated appealed the denial of its claim for remission of liquidated damages assessed by the government. The Board granted in part Sauer's cross-motion for summary judgment regarding the government's assessment of liquidated damages.
Material Facts
- The government awarded Sauer a Multiple Award Task Order Contract (MATOC) in 2007.
- Sauer submitted a proposal in response to a Request for Proposal (RFP) for the design and construction of the 82nd Airborne Division Headquarters.
- The RFP included a liquidated damages provision based on FAR Clause 52.211-12, stating liquidated damages of $4,365.81 per day for delays.
- The Task Order completion date was extended a total of 160 calendar days via eight modifications.
- The government assessed liquidated damages for the period starting November 17, 2013, through December 20, 2013, totaling $144,071.73.
- Sauer submitted a certified claim challenging the assessment of liquidated damages on September 6, 2019.
- The contracting officer issued a final decision denying Sauer’s claim on November 20, 2019.
Parties
- Appellant
- Sauer Incorporated
- Respondent Agency
- U.S. Army District, Savannah
- Contract Number
- W91278-07-D-0030
Full Legal Analysis
Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.
Holding & Legal Reasoning
The Board's holding, background, and procedural posture for this decision.
Issues Presented
Every issue the Board decided, with its determination, reasoning, and supporting authority.
Quantum & Recovery
The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.
Verified Authorities & Citations
Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.
Practitioner Takeaways
Practical guidance for contractors and counsel, distilled from the Board's ruling.
Similar Cases
Related decisions surfaced by semantic search across the full analyzed corpus.
Citation Graph
An interactive graph of this case's cited authorities, judge, agency, and related decisions.
Related Decisions
Same Judge
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026
- TYD ServicesNo. 64429, 64430July 8, 2026
- Granite Construction CompanyNo. 63667June 23, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439June 2, 2026
- Malika and Refa Environmental SolutionsNo. 63960December 8, 2025
Same Year
- Cellular Materials International, Inc.No. 61408December 27, 2021
- Meltech Corporation, Inc.No. 61706, 61768December 17, 2021
- Telos CorporationNo. 62950December 16, 2021
- General Dynamics Mission Systems, Inc.No. 62180-ADRDecember 13, 2021
- Adjuvant/Capital, LLCNo. 62760December 13, 2021
- Veteran Facility Services, LLCNo. 61855, 61983, 62386December 9, 2021
Same Issue
- Hensel Phelps Construction Co.No. 63316, 63397, 63398August 28, 2026
- J.A.M. Construction Services, Inc.No. 63378, 64226, 64439July 28, 2026
- ACC Construction Co., Inc.No. 63528, 64067July 16, 2026
- Healtheon, Inc.No. 63145July 24, 2025
- Gideon Contracting, LLCNo. 63561May 12, 2025
- ECC International Constructors, LLCNo. 59586April 18, 2025