62395

Sauer Incorporated

April 16, 2021Judge Stinson
Partially SustainedLiquidated DamagesDCAA Involved

Sauer Incorporated appealed the denial of its claim for remission of liquidated damages assessed by the government. The Board granted in part Sauer's cross-motion for summary judgment regarding the government's assessment of liquidated damages.

Material Facts

  • The government awarded Sauer a Multiple Award Task Order Contract (MATOC) in 2007.
  • Sauer submitted a proposal in response to a Request for Proposal (RFP) for the design and construction of the 82nd Airborne Division Headquarters.
  • The RFP included a liquidated damages provision based on FAR Clause 52.211-12, stating liquidated damages of $4,365.81 per day for delays.
  • The Task Order completion date was extended a total of 160 calendar days via eight modifications.
  • The government assessed liquidated damages for the period starting November 17, 2013, through December 20, 2013, totaling $144,071.73.
  • Sauer submitted a certified claim challenging the assessment of liquidated damages on September 6, 2019.
  • The contracting officer issued a final decision denying Sauer’s claim on November 20, 2019.

Parties

Appellant
Sauer Incorporated
Respondent Agency
U.S. Army District, Savannah
Contract Number
W91278-07-D-0030
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.