6249462495

Iqrar Ahmed and Partner Contracting Company

August 24, 2021Judge McIlmail
Sustained / Appellant PrevailedTermination for Default

Iqrar Ahmed and Partner Contracting Company challenged the government's termination of its contract for default and the denial of its claim for an extension of time. The Board sustained the appeal regarding the termination and deemed it a termination for convenience, while the extension claim was denied as moot.

Material Facts

  • The parties contracted for the appellant to deliver 25 shower blocks and 25 latrine blocks for $3,656,250.
  • The contract incorporated FAR 52.202-1 and FAR 52.212-4, which included provisions for termination for cause.
  • The contract specified delivery of the blocks '60 Days After Receipt Of Award' and defined the completion time as '60 working days' from receipt of a firm purchase order.
  • The appellant did not deliver the required number of compliant units by January 6, 2020, but had delivered at most two units.
  • The contracting officer issued a Show Cause Notice on January 7, 2020, and subsequently terminated the contract for cause on February 1, 2020.

Parties

Appellant
Iqrar Ahmed and Partner Contracting Company
Contract Number
FA4911-20-P-M011
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.