Flatiron/Dragados/Sukut Joint Venture

April 3, 2023Judge McNulty
Denied / Government PrevailedEquitable Adjustment (REA)

The ASBCA addressed the government's motion to dismiss claims by Flatiron/Dragados/Sukut Joint Venture regarding a contract dispute stemming from a bid protest. The Board denied the motion, allowing the claims to proceed.

Material Facts

  • The government awarded Contract No. W91238-17-C-0025 to FDS for the Isabella Lake Dam Safety Modification Project.
  • The contract incorporated the FAR clauses 52.233-3 and 52.242-14.
  • The contracting officer directed FDS to suspend performance pending resolution of a bid protest.
  • FDS submitted a request for an equitable adjustment seeking $9,812,107 due to delays and additional costs from the bid protest.
  • The contracting officer issued modifications extending the contract performance period and awarding FDS $133,716 for costs incurred during the stop work period.
  • FDS converted its REA into formal CDA claims, which were partially denied by the contracting officer.
  • FDS appealed the contracting officer's decisions to the ASBCA.

Parties

Appellant
Flatiron/Dragados/Sukut Joint Venture
Respondent Agency
U.S. Army Engineer District, Sacramento
Contract Number
Contract No. W91238-17-C-0025
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.