63076630776307863079

Betance Enterprises, Inc.

January 25, 2023Judge Stinson
Denied / Government PrevailedQuantum / Damages

Betance Enterprises, Inc. appealed four contracting officer's final decisions denying claims for additional costs incurred due to hailstorm damage to roofing systems. The Board granted the government's motion for summary judgment, denying the appellant's claims.

Material Facts

  • The government issued Solicitation No. W9128F-15-R-0016 for a firm-fixed-price Design-Build Single Award Task Order Contract for construction at Fort Carson, Colorado.
  • The contract incorporated by reference FAR 52.236-7, which states the contractor is responsible for all materials delivered and work performed until completion and acceptance.
  • The government awarded Task Order W9128F-17-F-0152 to BEI for roof repairs on September 22, 2017.
  • Hailstorms on June 13, 2018 and August 6, 2018 damaged roof repair and replacement work BEI was performing.
  • BEI submitted requests for equitable adjustment for additional costs incurred due to hailstorm damage.
  • The contracting officer issued final decisions denying BEI’s claims on August 19, 2021.

Parties

Appellant
Betance Enterprises, Inc.
Respondent Agency
U.S. Army Engineer District, Omaha
Contract Number
Contract No. W9128F-16-D-0003
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.