CBCA 1945

Heritage of America, LLC

Nov 28, 2011Judge VergilioDEPARTMENT OF VETERANS AFFAIRS
Not published in the listingRuled on a motion

Key Facts

Appellant
Heritage of America, LLC
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Vergilio
Case number
CBCA 1945
Decided
Nov 28, 2011The decision states Nov 28, 2011 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
Baker & Hostetler
Outcome
Ruled on a motion
The Board DENIES the agency's motion to dismiss.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Payment and interestJurisdiction and timelinessCosts and quantumContract interpretationChanges and equitable adjustment

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Hilary S. Cairnie and Dena S. Kessler and Udyogi A. Hangawatte
Baker & Hostetler
Washington, DC
For the respondent
William R. Korth and Philip Kauffman and Dennis Foley and L.T. Burleson and Carrie Parish
Office of the General Counsel, Department of Veterans Affairs
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision6 pages, 12,404 characters, read from the Board's own documentDecided Nov 28, 2011 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

MOTION TO DISMISS DENIED: November 28, 2011

CBCA 1945

HERITAGE OF AMERICA, LLC,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Hilary S. Cairnie, Dena S. Kessler, and Udyogi A. Hangawatte of Baker & Hostetler, LLP, Washington, DC, counsel for Appellant.

William R. Korth, Philip Kauffman, Dennis Foley, L.T. Burleson, and Carrie Parish, Office of the General Counsel, Department of Veterans Affairs, Washington, DC, counsel for Respondent.

Before Board Judges STERN, BORWICK, and VERGILIO.

VERGILIO, Board Judge.

On March 24, 2010, the Board received from Heritage of America, LLC (contractor or HOA) a notice of appeal concerning its contract, VA101(049A3)-V-0329, with the Department of Veterans Affairs (agency), under which the contractor provided vocational rehabilitation and employment services. The appeal was filed based upon a deemed denial, the contracting officer having failed within sixty days of receipt of a claim to issue a decision or indicate the period of time within which a decision would be issued. The agency filed a motion to dismiss “regarding matters either not properly before the Board or which have been mooted, waived, or implicitly resolved via accord and satisfaction[.]” The Board denies the agency’s motion.

2 CBCA 1945

The claim

In its certified claim (dated November 19, 2009) to the contracting officer, the contractor raises various theories of relief. Citing various examples, it asserts that the agency impeded the contractor’s performance, failed to pay amounts due, and caused increases to the contractor’s costs of performance. The claim prefaces the quantum section with two paragraphs:

HOA provides estimates in this section of the amounts to which it is entitled for the claims set forth above. Some of these costs, such as unpaid invoices and interest, change on a daily basis by their very nature.

The amounts are separately stated, and at the point VA considers the actual payment of specific claim items, HOA will work cooperatively with VA to identify any overlap.

Appeal File, Exhibit 7.1 at 31 (exhibits are in the appeal file). The claim enumerates nine categories for (or elements of) payment.

One: Regarding unpaid invoices, the claim states, VA owes HOA for unpaid invoices in the amount of $687,597.13, as of November 12, 2009. The exhibit referenced in the claim specifies a balance for invoices identified by date, invoice number, name, and class. This claim is for a sum certain, albeit a sum that could vary if the contractor receives payment from the agency. Exhibit I.A.1.1.

Exhibit 7.2 at 31 (and referenced Exhibit I.A.1.1).

Two: The claim seeks interest as required under the Prompt Payment Act, 31 U.S.C.

§ 3902(b) (2006), for invoices paid late. Further, the claim specifies: This interest is estimated to be $48,925 as of the end of September, 2009. In addition, VA is liable for penalties due on unpaid interest on late payments made, in an amount to be determined. Finally, VA is also liable for Prompt Payment Act interest on unpaid invoices to the date of this claim, and for Contract Disputes Act interest thereafter, to the date of payment.

Exhibit 7.2 at 31. With the exception of the unspecified penalties, these amounts the contractor seeks can be calculated as certain sums, if payments indeed are late and interest 3 CBCA 1945

triggering events identified. The claim indicates no penalty that the contractor has incurred for which it seeks reimbursement.

Three: The claim asserts entitlement to payment for orders placed under two service groups. An exhibit lists the amounts that VA should have paid, but has not paid, for these orders, because of its erroneous interpretation of the contract price tables. As of September 25, 2009, this amount is $50,540.76. Moreover, VA’s material breach, by virtue of nonpayment, means that HOA and its subcontractors have been unable to bring these cases to completion, and so together they are losing revenue in the amount of $227,423.05, as calculated on the same Exhibit on those cases. In addition, that same material breach means that HOA and its subcontractors have been unable to bring case management cases of 12 months and shorter duration to completion, and so they are together losing revenue in the amount of $1,055,544.41 on those cases. See Exhibit II.2. These sums constitute additional damages for breach of contract. Finally, HOA had to incur additional administrative costs in revising and submitting monthly invoices because they were divided by 12 months, rather than some other, larger number of months as designated by the regional office. An estimate of these costs, in the amount of $37,602.17 is set forth at Exhibit II.3.

Exhibit 7.2 at 31-32. The referenced claim exhibit II.2 does not make apparent the basis for the identified claim amounts. The referenced claim exhibit II.3 identifies five individuals, and for each the percentage of time over a given period spent on counselor billing corrections for case management and a dollar amount sought.

Four: The contractor asserts that start-up was delayed for approximately four months (from mid-September to mid-January). It maintains that continuing overhead costs incurred during that period could not be fully recovered through the priced contract work. “These cases are estimated on Exhibit II.4. They amounted to $556,390.69 computed for the period September 1 through December 31, 2008.” The referenced supporting exhibit specifies costs for various offices as well as operating costs, with costs summing to the claimed amount. Exhibit 7.2 at 32 (and referenced Exhibit II.4).

Five: As a separate item of its claim, identified as costs for a rapid response team, the contractor states that the agency caused delays to the contractor in obtaining counselor approvals, and that the contractor incurred additional costs because of the delays. “These costs, estimated to be $38,022.72, are set forth in Exhibit II.5.” In support of this amount, 4 CBCA 1945

the submission identifies costs for travel, hotels, per diems, and parking, as well as for tips, a subcontractor fee, and a salary. Exhibit 7.2 at 32 (and referenced Exhibit II.5).

Six: The contractor claims that it incurred costs of $98,493.54 for temporary labor to process counselor approvals. While the contractor claims that an estimated 30% of those costs are related to the normal processing costs, it seeks $68,948.48 (an exact amount, stated to be an estimated 70% of the incurred costs) as costs incurred beyond those anticipated under the contract because of various agency activities in one location. The claim references no supporting documentation for this item. Exhibit 7.2 at 32.

Seven: The contractor seeks $10,591.96 for what it describes as additional testing costs. That is, the contractor maintains that agency individuals in the New England area imposed additional and unnecessary tests for which the contractor incurred the stated costs of subcontractors, itemized in an exhibit. The contractor expressly “reserves the right to amend this amount as additional claims for additional tests are received.” Exhibit 7.2 at 32 (and referenced Exhibit II.6). To date, the contractor has not indicated that it has amended its claim relating to this specific quantum claim element or the more broadly worded aspects of its claim that allege agency interference with its ability to perform under the contract. Eight: The contractor contends that the agency failed to order some guaranteed minimums. The claim itemizes the shortfalls, associated dollar amounts, and bases for the calculations. The contractor seeks $71,515 for this item. Exhibit 7.2 at 32.

Nine: The contractor seeks compensation for “additional financing costs” described as interest incurred to finance amounts paid late by the agency. The claim computes the amount at $38,759.29, for receivables over thirty days unpaid as of October 31, 2009, while stating that the amount due under this claim should be net of Prompt Payment Act interest. Exhibit 7.2 at 33 (and referenced Exhibit II.7).

Motion to Dismiss

The agency identifies various “points and authorities/arguments” in support of its motion to dismiss.

Sum certain

Asserting that a proper claim for relief must involve a sum certain, the agency states: “All the Complaint’s allegations supported by estimations, approximations, and guesswork, despite having figures assigned, must fail as not being properly before the Board, including 5 CBCA 1945

Delayed Start-Up Costs, Rapid Response Team, and Additional Testing Costs.” Agency Motion at 6.

Contrary to the broad assertions of the agency, each element of the claim identifies specific amounts for relief. The claim seeks a sum certain. An exception is the reference in claim element two to penalties in an amount to be determined. Without an asserted factual or legal basis or a sum certain for this element, this is not a proper element under the existing claim. But for this item, this claim is properly before the Board.

Waiver

In seeking to dismiss portions of the claim, the agency relies upon waiver: “In negotiating and accepting payments for past invoices and interests over the past year, Appellant has waived any defaults or defects in the invoices, interest, or payment.” The agency focuses this allegation upon unpaid invoices. However, the agency has provided neither basic factual support nor legal analysis that permits this assertion of waiver to be sustained.

Accord and satisfaction

As a basis in its motion to dismiss, the agency raises accord and satisfaction “as the Appellant agreed to negotiate over the invoices/billings past due and unpaid and has explicitly accepted both the Government’s payments as well as the Government’s overtures and efforts to reduce that quantum further, far below what the Complaint originally alleged.” Factually and legally, this assertion by the agency remains ill-supported. Without specifics, it is unclear which claim elements or portions of the claim the agency deems to be resolved. Limiting claims to contract line items (CLINS) The agency attempts to limit the contractor’s claim: “Appellant cannot present claims outside of the contract CLINS; the Appellant, as any contractor, may not unilaterally create or modify the contract to add equipment, labor, or related charges in addition to the line items and obligate the Government to provide compensation.” While the agency is correct that a contractor may not unilaterally create or modify a contract, this contractor is claiming that the agency unilaterally breached or modified the contract. Under theories of breach and constructive change, the contractor asserts entitlement to costs it incurred as a result of the agency’s actions which were not contemplated under the terms and conditions of the contract. Factually and legally, the agency has not demonstrated that these causes of action must fail. ______________________________

______________________________ ______________________________

6 CBCA 1945

Anti-Deficiency Act

Finally, the agency posits that there are no Anti-Deficiency Act, 31 U.S.C. § 1341, issues when the Government provides and has appropriated funds to pay for obligations. The contractor alludes to the Anti-Deficiency Act in support of its interpretation of the underlying contract. In particular, the contractor contends that the agency could not be obtaining services over multiple fiscal years without appropriate authorization and funding. Further, the contractor relies upon its reading of the Act to bolster its interpretation of the contract that services were priced and to be paid for in increments of at most twelve months, not periods in excess of one year as the agency maintains. Because the claim does not raise the Act as an element of the claim, but only as a factor in contract interpretation, the agency’s motion is misplaced.

Decision

The Board DENIES the agency’s motion to dismiss. The present case is focused upon the elements of the underlying claim; there is not an amended claim (or contracting officer decision) or an amended complaint. The request for unspecified penalties in an unspecified amount in claim element two is premature, given that the claim fails to specify any penalty that the contractor has incurred or will incur for which it seeks compensation. JOSEPH A. VERGILIO

Board Judge

We concur:

JAMES L. STERN

Board Judge

ANTHONY S. BORWICK

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Heritage of America, LLC, CBCA 1945. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.