CBCA 2834

Monster Government Solutions, LLC

May 24, 2012Judge DanielsDEPARTMENT OF JUSTICE
Not published in the listingGranted

Key Facts

Appellant
Monster Government Solutions, LLC
Respondent agency
DEPARTMENT OF JUSTICE
Judge
Daniels
Case number
CBCA 2834
Decided
May 24, 2012The decision states May 24, 2012 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
Greenberg Traurig, LLP
Outcome
Granted
GRANTED
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from that line, because the decision's text states no operative ruling we could isolate. No model is involved.

Topics

Jurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions.

Appearances

For the appellant
Jacob B. Pankowski and William M. Jack
Greenberg Traurig, LLP
Washington, DC
For the respondent
Morton J. Posner and Barry C. Hansen
Office of General Counsel, Justice Management Division, Department of Justice
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision2 pages, 2,247 characters, read from the Board's own documentDecided May 24, 2012 on its own faceRespondent DEPARTMENT OF JUSTICE Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

2 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

GRANTED: May 24, 2012

CBCA 2834

MONSTER GOVERNMENT SOLUTIONS, LLC,

Petitioner,

v.

DEPARTMENT OF JUSTICE,

Respondent.

Jacob B. Pankowski and William M. Jack of Greenberg Traurig, LLP, Washington,

DC, counsel for Petitioner.

Morton J. Posner and Barry C. Hansen, Office of General Counsel, Justice

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Management Division, Department of Justice, Washington, DC, counsel for Respondent.

Before Board Judges DANIELS (Chairman), VERGILIO, and STEEL.

DANIELS, Board Judge.

Monster Government Solutions, LLC (MGS), petitions the Board to direct a Department of Justice (DOJ) contracting officer to issue a decision no later than June 4, 2012, with regard to MGS’s October 6, 2011, certified claim in the amount of $512,009.63 under a contract and delivery order for the provision of an automated personnel recruiting system. In response, DOJ states that the contracting officer “will issue a decision no later than June 4, 2012.”

The Contract Disputes Act provides that when in receipt of a certified claim in an amount greater than $100,000, a contracting officer shall, within sixty days, either issue a _________________________

________________________ _________________________

2 CBCA 2834

decision on the claim or notify the contractor of the time within which a decision will be issued. 41 U.S.C. § 7103(f)(2) (West Supp. 2011). If the contracting officer chooses the second of these alternatives, his decision “shall be issued within a reasonable time, in accordance with regulations prescribed by the agency, taking into account such factors as the size and complexity of the claim and the adequacy of information in support of the claim provided by the contractor.” Id. § 7103(f)(3). The statute also provides that “[a] contractor may request the tribunal concerned to direct a contracting officer to issue a decision in a specified period of time, as determined by the tribunal concerned, in the event of undue delay on the part of the contracting officer.” Id. § 7103(f)(4).

Given that the petition is not opposed by DOJ, the Board GRANTS it. We direct the contracting officer to issue a decision on the claim no later than June 4, 2012.

STEPHEN M. DANIELS

Board Judge

We concur:

JOSEPH A. VERGILIO

Board Judge

CANDIDA S. STEEL

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Monster Government Solutions, LLC, CBCA 2834. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.